High Services Inc. is an international firm that has more than 100,000 employees that work in various parts of the globe. With the expansion of the number of customers, the firm has decided to implement an advanced Customer Relationship Management (CRM) system and social CRM is one of the components of the same. There are various resources that will be associated with the CRM project, such as, Natalie, Program Sponsor, Ito, Program Manager, Ben, CIO and Project Sponsor, George, Marketing Manager of social CRM.  

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The report includes the project charter and also described details of the project stakeholders and project scope.

Social CRM for High Services Inc

The numbers of customers that are engaged with High Services Inc. are expanding at a rapid rate. With the current systems and the nature of operations, it is becoming challenging to fulfill the needs and demands of the customers having a negative impact on their engagement with the company.

In order to achieve the business goals and objectives, it is essential to understand the needs of the customers. There shall be an automated system in place that may analyze the customer information and also maintain the required interaction level with the customers of the organization.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Social CRM is an attempt to fulfill these objectives through automated system and mechanisms that will analyze customer information and will enhance the engagement with the organization.

  • There shall be no major or critical defects present in the end product and the functional aspects shall be met.
  • The social CRM system must stick to the quality standards and ethical practices (Roberts-Lombard, 2012).
  • The expectations and demands of the customers shall be met.
  • There shall be no performance issues in the end-product that will be used by the end-users.

The activities associated with the design, development, testing, integration and deployment will be executed by the members of the project team.

The activities related with negotiations, marketing and advertising will not be carried out by the members of the project team.

  • Project Plan: This document will include the details of the project estimates, project team and the project stakeholder along with the methodology and approach (Singh, 2015).
  • System Design: The document will include the design diagram and the wireframes.
  • Source Code: The coding details of the system that will be developed.
  • Test Plan: The plan will comprise of the testing activities that will be carried out, test methodology and defect tracking mechanism.
  • Closure Report: The project activities that are carried out by the team members will be included in the report.  

Milestone

     Milestone One: Finalize requirements

      Milestone Two: Project Charter

      Milestone Three: Project Plan

      Milestone Four: Finalize implementation tools and techniques

      Milestone Five: System Design & Source Code

      Milestone Six: Defect Report

      Milestone Seven: Implementation Plan

      Milestone Eight: Closure Report

  • The environment and the equipment required for the execution of the project tasks will be arranged in advanced.
  • $2,000,000 will be allocated for the completion of all the project tasks and activities.
  • Six months will be assigned for the completion of all the project tasks and activities (Peppard, 2010). 

$2,000,000 will be allocated for the completion of all the project tasks and activities. $300,000 will be assigned for the internal staffing expenses.

Name of the Team Member

Role

Set of Responsibilities

Ben

Project Sponsor and CIO

Providing the project funds and the specifications

George

Marketing Manager

Designing of the marketing plan

AA

Project Manager

Planning, estimations, resourcing, monitoring and closure

BB

Finance Office

Budgeting of the project

CC

Business Analyst

Feasibility analysis and management of the risks

DD

Data Scientist

Gathering and analysis of customer information

EE

Project Developer

Source code, unit testing

FF

Tester

System, integration, regression and performance testing

GG

Designer

System designing

HH

Implementation Expert

Implementation and management of the changes

Resource Name

Type

Initials

Max. Units

Std. Rate

Project Manager

Work

PM

100%

$ 420.00/hr

Business Analyst

Work

BA

100%

$ 350.00/hr

Data Scientist

Work

DS

100%

$ 400.00/hr

Project Developer

Work

PD

100%

$ 325.00/hr

Tester

Work

TE

100%

$ 300.00/hr

Designer

Work

DE

100%

$ 315.00/hr

Implementation Expert

Work

IE

100%

$ 330.00/hr

Finance Officer

Work

FO

100%

$ 375.00/hr

 

 

RACI stands for Responsibility, Accountability, Contribution and Informed. The resources that will be engaged with the project will be associated and involved in all the project activities in one form or the other (Tirkey, 2012). The RACI matrix that has been illustrated below explains the tasks that will be covered by the project team members.

Ben

George

AA

BB

CC

DD

EE

FF

GG

HH

Project Charter

I

I

R/A

I

C

I

I

I

I

I

Feasibility Analysis

I

I

A

I

R

I

C

I

C

C

Planning and Estimations

C

I

R/A

C

C

I

C

C

C

C

Budgeting

C

I

A

R

I

I

I

I

I

I

Risk Management

I

I

C

C

A/R

I

C

C

C

C

Information Gathering and Analysis

A

C

A

I

I

R/A

C

C

C

C

System Development

I

I

I

I

C

I

R/A

C

C

C

System Designing

I

I

I

I

I

I

C

C

R/A

C

Testing Activities

I

I

A

I

I

I

A

R/A

C

C

System Implementation

I

I

I

I

I

I

C

C

C

R/A

Closure Activities

C

I

R/A

C

A

I

C

C

C

C

Task-wise budget

WBS

Task Name

Duration

Start

Finish

Cost

1

Social CRM Project 

132 days

Fri 06-10-17

Mon 09-04-18

$ 711,160.00

1.1

   Initiation of the project

6 days

Fri 06-10-17

Fri 13-10-17

$ 105,280.00

1.1.1

       Feasibility Study – Technical

4 days

Fri 06-10-17

Wed 11-10-17

$ 24,640.00

1.1.2

       Feasibility Analysis – Operational

4 days

Fri 06-10-17

Wed 11-10-17

$ 24,640.00

1.1.3

       Feasibility Analysis – Economical

4 days

Fri 06-10-17

Wed 11-10-17

$ 24,640.00

1.1.4

       Chartering Tasks

4 days

Fri 06-10-17

Wed 11-10-17

$ 24,640.00

1.1.5

       Submission of the charter

2 days

Thu 12-10-17

Fri 13-10-17

$ 6,720.00

1.1.6

       Milestone One: Project Charter

0 days

Fri 13-10-17

Fri 13-10-17

$ 0.00

1.2

   Planning & Analysis

14 days

Mon 16-10-17

Thu 02-11-17

$ 217,240.00

1.2.1

       Information Collection & Investigation

10 days

Mon 16-10-17

Fri 27-10-17

$ 32,000.00

1.2.2

       Analysis of requirements

8 days

Mon 16-10-17

Wed 25-10-17

$ 74,880.00

1.2.3

       Project Scope Statement

8 days

Mon 16-10-17

Wed 25-10-17

$ 49,280.00

1.2.4

       Budget & Schedule Estimation

3 days

Mon 16-10-17

Wed 18-10-17

$ 19,080.00

1.2.5

       Assessment of risks

3 days

Mon 16-10-17

Wed 18-10-17

$ 18,480.00

1.2.6

       Communication plan and team selection

3 days

Mon 16-10-17

Wed 18-10-17

$ 10,080.00

1.2.7

       Roles & Responsibilities Allocation

4 days

Mon 30-10-17

Thu 02-11-17

$ 13,440.00

1.2.8

       Milestone Two: Project Plan

0 days

Thu 02-11-17

Thu 02-11-17

$ 0.00

1.3

   Project Execution – Design & Development

62 days

Fri 03-11-17

Mon 29-01-18

$ 187,520.00

1.3.1

       UI/EX aspects of the system

5 days

Fri 03-11-17

Thu 09-11-17

$ 25,600.00

1.3.2

       Review of the design

4 days

Fri 10-11-17

Wed 15-11-17

$ 13,440.00

1.3.3

       Source code

30 days

Thu 16-11-17

Wed 27-12-17

$ 78,000.00

1.3.4

       Setting up of the database

10 days

Thu 28-12-17

Wed 10-01-18

$ 26,000.00

1.3.5

       Integration of front end and back end

10 days

Thu 11-01-18

Wed 24-01-18

$ 26,000.00

1.3.6

       Review of the source code

3 days

Thu 25-01-18

Mon 29-01-18

$ 18,480.00

1.3.7

       Milestone Three: System Design & Source Code

0 days

Mon 29-01-18

Mon 29-01-18

$ 0.00

1.4

   Testing & Integration

18 days

Tue 30-01-18

Thu 22-02-18

$ 44,400.00

1.4.1

       Integration of the modules

5 days

Tue 30-01-18

Mon 05-02-18

$ 13,200.00

1.4.2

       System Integration Testing

3 days

Tue 06-02-18

Thu 08-02-18

$ 7,200.00

1.4.3

       Regression testing

2 days

Fri 09-02-18

Mon 12-02-18

$ 4,800.00

1.4.4

       Security and Performance Testing

4 days

Tue 13-02-18

Fri 16-02-18

$ 9,600.00

1.4.5

       Load testing

2 days

Mon 19-02-18

Tue 20-02-18

$ 4,800.00

1.4.6

       Submission of bugs and defects

2 days

Wed 21-02-18

Thu 22-02-18

$ 4,800.00

1.4.7

       Milestone Four: Defect Report

0 days

Thu 22-02-18

Thu 22-02-18

$ 0.00

1.5

   Implementation & Control 

20 days

Fri 23-02-18

Thu 22-03-18

$ 72,640.00

1.5.1

       Decision on the system changes

3 days

Fri 23-02-18

Tue 27-02-18

$ 7,920.00

1.5.2

       Change management

3 days

Wed 28-02-18

Fri 02-03-18

$ 7,920.00

1.5.3

       Change reinforcement

2 days

Mon 05-03-18

Tue 06-03-18

$ 5,280.00

1.5.4

       Measurement of performance 

2 days

Wed 07-03-18

Thu 08-03-18

$ 6,720.00

1.5.5

       Reviews and walkthroughs

4 days

Fri 09-03-18

Wed 14-03-18

$ 24,640.00

1.5.6

       System inspections

3 days

Thu 15-03-18

Mon 19-03-18

$ 10,080.00

1.5.7

       Auditing activities

3 days

Tue 20-03-18

Thu 22-03-18

$ 10,080.00

1.5.8

       Milestone Five: Implementation Plan

0 days

Thu 22-03-18

Thu 22-03-18

$ 0.00

1.6

   Closure Phase

12 days

Fri 23-03-18

Mon 09-04-18

$ 84,080.00

1.6.1

       User Trainings

6 days

Fri 23-03-18

Fri 30-03-18

$ 36,960.00

1.6.2

       Maintenance and support planning

2 days

Fri 23-03-18

Mon 26-03-18

$ 5,600.00

1.6.3

       Acceptance and Sign offs

3 days

Fri 23-03-18

Tue 27-03-18

$ 10,080.00

1.6.4

       System documentation and closure report

6 days

Mon 02-04-18

Mon 09-04-18

$ 31,440.00

1.6.5

       Milestone Six: Closure Report

0 days

Mon 09-04-18

Mon 09-04-18

$ 0.00

Resource-wise budget

WBS

Task Name

Duration

Resource Names

Cost

1

Social CRM Project 

132 days

$ 711,160.00

1.1

   Initiation of the project

6 days

$ 105,280.00

1.1.1

       Feasibility Study – Technical

4 days

Business Analyst, Project Manager

$ 24,640.00

1.1.2

       Feasibility Analysis – Operational

4 days

Business Analyst, Project Manager

$ 24,640.00

1.1.3

       Feasibility Analysis – Economical

4 days

Business Analyst, Project Manager

$ 24,640.00

1.1.4

       Chartering Tasks

4 days

Project Manager, Business Analyst

$ 24,640.00

1.1.5

       Submission of the charter

2 days

Project Manager

$ 6,720.00

1.1.6

       Milestone One: Project Charter

0 days

$ 0.00

1.2

   Planning & Analysis

14 days

$ 217,240.00

1.2.1

       Information Collection & Investigation

10 days

Data Scientist

$ 32,000.00

1.2.2

       Analysis of requirements

8 days

Business Analyst, Project Manager, Data Scientist

$ 74,880.00

1.2.3

       Project Scope Statement

8 days

Project Manager, Business Analyst

$ 49,280.00

1.2.4

       Budget & Schedule Estimation

3 days

Finance Officer, Project Manager

$ 19,080.00

1.2.5

       Assessment of risks

3 days

Business Analyst, Project Manager

$ 18,480.00

1.2.6

       Communication plan and team selection

3 days

Project Manager

$ 10,080.00

1.2.7

       Roles & Responsibilities Allocation

4 days

Project Manager

$ 13,440.00

1.2.8

       Milestone Two: Project Plan

0 days

$ 0.00

1.3

   Project Execution – Design & Development

62 days

$ 187,520.00

1.3.1

       UI/EX aspects of the system

5 days

Designer, Implementation Expert

$ 25,600.00

1.3.2

       Review of the design

4 days

Project Manager

$ 13,440.00

1.3.3

       Source code

30 days

Project Developer

$ 78,000.00

1.3.4

       Setting up of the database

10 days

Project Developer

$ 26,000.00

1.3.5

       Integration of front end and back end

10 days

Project Developer

$ 26,000.00

1.3.6

       Review of the source code

3 days

Project Manager, Business Analyst

$ 18,480.00

1.3.7

       Milestone Three: System Design & Source Code

0 days

$ 0.00

1.4

   Testing & Integration

18 days

$ 44,400.00

1.4.1

       Integration of the modules

5 days

Implementation Expert

$ 13,200.00

1.4.2

       System Integration Testing

3 days

Tester

$ 7,200.00

1.4.3

       Regression testing

2 days

Tester

$ 4,800.00

1.4.4

       Security and Performance Testing

4 days

Tester

$ 9,600.00

1.4.5

       Load testing

2 days

Tester

$ 4,800.00

1.4.6

       Submission of bugs and defects

2 days

Tester

$ 4,800.00

1.4.7

       Milestone Four: Defect Report

0 days

$ 0.00

1.5

   Implementation & Control 

20 days

$ 72,640.00

1.5.1

       Decision on the system changes

3 days

Implementation Expert

$ 7,920.00

1.5.2

       Change management

3 days

Implementation Expert

$ 7,920.00

1.5.3

       Change reinforcement

2 days

Implementation Expert

$ 5,280.00

1.5.4

       Measurement of performance 

2 days

Project Manager

$ 6,720.00

1.5.5

       Reviews and walkthroughs

4 days

Project Manager, Business Analyst

$ 24,640.00

1.5.6

       System inspections

3 days

Project Manager

$ 10,080.00

1.5.7

       Auditing activities

3 days

Project Manager

$ 10,080.00

1.5.8

       Milestone Five: Implementation Plan

0 days

$ 0.00

1.6

   Closure Phase

12 days

$ 84,080.00

1.6.1

       User Trainings

6 days

Business Analyst, Project Manager

$ 36,960.00

1.6.2

       Maintenance and support planning

2 days

Business Analyst

$ 5,600.00

1.6.3

       Acceptance and Sign offs

3 days

Project Manager

$ 10,080.00

1.6.4

       System documentation and closure report

6 days

Project Developer, Implementation Expert

$ 31,440.00

1.6.5

       Milestone Six: Closure Report

0 days

$ 0.00

Risk Name

Description

Type

Probability (5: Highest and 1: lowest)

Impact (5: Highest and 1: lowest)

Rank

Schedule Overrun

Increased time in the completion of project activities as compared to the estimated schedule

Negative

2

5

10

Technical Failure

Failure of faults in technical tools and equipment

Negative

4

4

16

Operational Mistake

Execution of an operational error by a user

Negative

4

3

12

Security Attack

Attacks on information, database or networks

Negative

3

4

12

Budget Overrun

Increased costs in association with the project activities as compared to the estimated budget

Negative

2

5

10

Resource Risk

Increased productivity levels of the employees as compared to the estimated values leading to completion of the project tasks before time

Positive

1

4

4

Recommendations and Conclusion 

Social CRM is a project that has a lot of significance for High Services Inc. There shall be adequate planning and analysis involved in the project to make sure that the project goals and objectives are achieved. There shall also be management methodology such as Project Management Body of Knowledge (PMBOK) applied to make sure that the management tasks are easily executed. The communication mode and strategies must be designed in such a manner that there is always clarity maintained among the members of the project team.

References

Adalikwu, Chris. 2012. “Customer Relationship Management And Customer Satisfaction”. AFRICAN JOURNAL OF BUSINESS MANAGEMENT 6 (22). doi:10.5897/ajbm12.634.

Davis, Kate. 2017. “An Empirical Investigation Into Different Stakeholder Groups Perception Of Project Success”. International Journal Of Project Management 35 (4): 604-617. doi:10.1016/j.ijproman.2017.02.004.

Goldsmith, Ronald E. 2010. “The Goals Of Customer Relationship Management”. International Journal Of Customer Relationship Marketing And Management 1 (1): 16-27. doi:10.4018/jcrmm.2010090402.

Khodakarami, Farnoosh, and Yolande E. Chan. 2014. “Exploring The Role Of Customer Relationship Management (CRM) Systems In Customer Knowledge Creation”. Information & Management 51 (1): 27-42. doi:10.1016/j.im.2013.09.001.

Levin, Ginger. 2014. “Managing Stakeholder Expectations For Project Success: A Knowledge Integration Framework And Value Focused Approach”. Project Management Journal 45 (6): e3-e3. doi:10.1002/pmj.21464.

Mitchell, Ronald K., Harry J. Van Buren, Michelle Greenwood, and R. Edward Freeman. 2015. “Stakeholder Inclusion And Accounting For Stakeholders”. Journal Of Management Studies 52 (7): 851-877. doi:10.1111/joms.12151.

Peppard, Joe. 2010. “Customer Relationship Management (CRM) In Financial Services”. European Management Journal 18 (3): 312-327. doi:10.1016/s0263-2373(00)00013-x.

Roberts-Lombard, Mornay. 2012. “Exploring The Relationship Between Trust, Commitment And Customer Loyalty Through The Intervening Role Of Customer Relationship Management (CRM)”. African Journal Of Business Management 6 (10). doi:10.5897/ajbm11.2562.

Santouridis, Ilias, and Androniki Veraki. 2017. “Customer Relationship Management And Customer Satisfaction: The Mediating Role Of Relationship Quality”. Total Quality Management & Business Excellence 28 (9-10): 1122-1133. doi:10.1080/14783363.2017.1303889.

Singh, Anurag. 2015. “Drive Customer Experience For Relationship Management Through Actionable Social CRM”. International Journal Of Customer Relationship Marketing And Management 6 (4): 57-76. doi:10.4018/ijcrmm.2015100104.

Tirkey, Manish Roy. 2012. “The People And CRM (Customer Relationship Management)”. IOSR Journal Of Business And Management 5 (2): 27-28. doi:10.9790/487x-0522728.

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP