Project Plan For Developing A Knowledge Management System By Company X

Work Breakdown Structure (WBS)

The company X, a Sydney based IT service providing company is nominated for this report. This report depicts development of a detail project plan for a knowledge system gathering expertise. Complexity of the project plan is reduced by breaking the entire project into small 5 phases-initiation, planning, execution, monitoring and control and project closure. The total time allocated to complete the knowledge system is 4 months. in order to complete the project total $150,000 budget will be needed. The project is expected to be initiated on 15th March, 2021.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

WBS is defined as a project management technique, used by the project team members widely to reduce the project complexity. In order to make the project simpler and easy manageable, the WBS technique is used. WBS is known as deliverable based project structure. It presents the hierarchical structure of the project. WBS helps to define and organize the work required. It helps to facilitate the work requirements and generates visuals of the overall project scope. An accurate WBS helps to reduce the possibilities of risk occurrences. For this project a WBS is developed.  The work breakdown structure of the project is presented here-

 

Figure 1: work breakdown structure for the project

(Source: created by author)

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The project team will take 4 months to complete the project activities considering fixed Saturday and Sunday off and 5 days with 8 hrs working period.

The project duration is calculated using the MS project software. Once the duration for each activity is allocated based on project requirements the total duration comes automatically. For this project a critical path is shows below-

 

Figure 2: Critical path for the project

(Source: created by author)

The red line shows the critical path. after calculating the critical path value arrives as 120. Critical path is the longest path that, a project manager and team can follow to complete the project. For this project, the critical path value is 120 days. For this project, the

According to PMBOK, critical path is a method used to model projects where the project manager can input all essential factors. In other words, it is the longest path or time that, a project team may take to complete a project. Critical path method is a technique, where project manager and team can identify necessary activities for project completion and also determine scheduling flexibilities. For this project CPM is used to improve future opportunities, facilitate more active resource management and assist the project team to avoid probable bottlenecks. The critical path for this project is calculated using 4 steps. These stages are mentioned in the below section-

Critical Path Method (CPM)

Step 1- the start and end time next to each activity should be placed

Step 2: The connection among the activities should be shown with arrows.

Step 3- After that, depending on the end time of the last activity in the activity sequence to calculate the duration of the complete sequence

Step 4- The sequence of activities with maximum duration is determined as the critical path. For this project, the value of the longest path is 120.

Gantt chart is a bar chart which illustrates project schedule and also display the activities with respect to time. It also shows the dependencies among the dependencies among the activities and duration for each activity. For designing he knowledge management system, gantt chart is used to improve team collaboration, manage tasks, manage probable resources, plan and track the project progress more easily and effectively.  

The overall budget and resources are allocated depending on the expertise, skills and area of interest of each resource. For this project 8 human resources and 2 physical resources (software cost and testing cost) are considered. Calculating which the total budget has become $150,000. The overall project gantt chart is shows in the below section-

WBS

Task Name

Duration

Start

Finish

Resource Names

Cost

0

Knowledge system project schedule

120 days

Tue 15/03/22

Mon 29/08/22

$150,000.00

1

   Initiation

6 days

Tue 15/03/22

Tue 22/03/22

$4,712.00

1.1

      Feasibility analysis

1 day

Tue 15/03/22

Tue 15/03/22

Project manager

$520.00

1.2

      Specify project constraints

1 day

Wed 16/03/22

Wed 16/03/22

Project coordinator

$464.00

1.3

      Analyze triple constraints

2 days

Wed 16/03/22

Thu 17/03/22

Project manager

$1,040.00

1.4

      Current productivity analysis

1 day

Thu 17/03/22

Thu 17/03/22

Project coordinator

$464.00

1.5

      Current technical platform analysis

1 day

Fri 18/03/22

Fri 18/03/22

Project coordinator

$464.00

1.6

      Identify project resources

2 days

Fri 18/03/22

Mon 21/03/22

Senior network consultant

$800.00

1.7

      Performance evaluation

1 day

Mon 21/03/22

Mon 21/03/22

Senior system engineer

$440.00

1.8

      Allocating team

1 day

Tue 22/03/22

Tue 22/03/22

Project manager

$520.00

1.9

      Milestone 1- PID handover to CTO

0 days

Tue 22/03/22

Tue 22/03/22

$0.00

2

   Planning

24 days

Wed 23/03/22

Mon 25/04/22

$12,048.00

2.1

      Feasibility analysis

1 day

Wed 23/03/22

Wed 23/03/22

Project coordinator

$464.00

2.2

      Azure cloud system specification

3 days

Thu 24/03/22

Mon 28/03/22

Project manager

$1,560.00

2.3

      quality planning

2 days

Tue 29/03/22

Wed 30/03/22

Project coordinator

$928.00

2.4

      schedule planning

2 days

Thu 31/03/22

Fri 01/04/22

Project coordinator

$928.00

2.5

      Design questionnaire

3 days

Mon 04/04/22

Wed 06/04/22

Project manager

$1,560.00

2.6

      Conduct primary survey

1 day

Thu 07/04/22

Thu 07/04/22

Senior system engineer

$440.00

2.7

      Gathering information

1 day

Fri 08/04/22

Fri 08/04/22

Seniors DevOps consultant

$416.00

2.8

      Effective data interpretation

2 days

Fri 08/04/22

Mon 11/04/22

Senior system engineer

$880.00

2.9

      Management training planning

2 days

Tue 12/04/22

Wed 13/04/22

Project coordinator

$928.00

2.10

      Administrative training

1 day

Thu 14/04/22

Thu 14/04/22

Project coordinator

$464.00

2.11

      Network monitoring

3 days

Fri 15/04/22

Tue 19/04/22

Project manager

$1,560.00

2.12

      Intranet monitoring and analysis

2 days

Wed 20/04/22

Thu 21/04/22

Project manager

$1,040.00

2.13

      System design setup

2 days

Fri 22/04/22

Mon 25/04/22

Senior system engineer

$880.00

2.14

      M2- completion of project planning

0 days

Mon 25/04/22

Mon 25/04/22

$0.00

3

   Design and execution

72 days

Tue 26/04/22

Wed 03/08/22

$82,456.00

3.1

      Deployment planning

5 days

Tue 26/04/22

Mon 02/05/22

Senior network consultant

$2,000.00

3.2

      Setup

3 days

Tue 03/05/22

Thu 05/05/22

Project manager

$1,560.00

3.3

      Server

5 days

Fri 06/05/22

Thu 12/05/22

Project manager

$2,600.00

3.4

      Networking equipment

6 days

Fri 13/05/22

Fri 20/05/22

Project coordinator

$2,784.00

3.5

      Intranet infrastructure

4 days

Mon 23/05/22

Thu 26/05/22

Senior network consultant

$1,600.00

3.6

      Acquisition

8 days

Fri 27/05/22

Tue 07/06/22

$53,880.00

3.6.1

         Software

3 days

Fri 27/05/22

Tue 31/05/22

Project manager, Software cost[1]

$51,560.00

3.6.2

         Other required platforms

5 days

Wed 01/06/22

Tue 07/06/22

Project coordinator

$2,320.00

3.7

      Perquisite’s verification plan

6 days

Wed 08/06/22

Wed 15/06/22

Senior system engineer

$2,640.00

3.8

      Email verification

5 days

Thu 16/06/22

Wed 22/06/22

Senior network consultant

$2,000.00

3.9

      Inventory management plan

4 days

Thu 23/06/22

Tue 28/06/22

Senior network consultant

$1,600.00

3.10

      Hardware and software deployment

5 days

Wed 29/06/22

Tue 05/07/22

Project manager

$2,600.00

3.11

      UX/UI design

5 days

Wed 06/07/22

Tue 12/07/22

Seniors DevOps consultant

$2,080.00

3.12

      System customization

2 days

Wed 13/07/22

Thu 14/07/22

Senior system engineer

$880.00

3.13

      Easy navigation

2 days

Fri 15/07/22

Mon 18/07/22

Azure cloud consultant

$864.00

3.14

      Final Mockup design

3 days

Tue 19/07/22

Thu 21/07/22

Azure engineer

$1,272.00

3.15

      Front end design done

4 days

Fri 22/07/22

Wed 27/07/22

Azure engineer

$1,696.00

3.16

      Backend connectivity to cloud server

5 days

Thu 28/07/22

Wed 03/08/22

Principle cloud consultant

$2,400.00

3.17

      M3- Complete running website execution

0 days

Wed 03/08/22

Wed 03/08/22

$0.00

4

   Monitoring and controlling

14 days

Thu 04/08/22

Tue 23/08/22

$47,696.00

4.1

      Unit testing

4 days

Thu 04/08/22

Tue 09/08/22

Principle cloud consultant

$1,920.00

4.2

      integrated testing

3 days

Wed 10/08/22

Fri 12/08/22

Senior network consultant

$1,200.00

4.3

      security testing

2 days

Mon 15/08/22

Tue 16/08/22

Senior system engineer

$880.00

4.4

      Functional testing

2 days

Wed 17/08/22

Thu 18/08/22

Azure engineer

$848.00

4.5

      System testing

3 days

Fri 19/08/22

Tue 23/08/22

Project coordinator, testing cost[1]

$41,808.00

4.6

      Acceptance testing

2 days

Fri 19/08/22

Mon 22/08/22

Project manager

$1,040.00

4.7

      Milestone 4- Knowledge system testing completion

0 days

Thu 18/08/22

Thu 18/08/22

$0.00

5

   Closure

4 days

Wed 24/08/22

Mon 29/08/22

$3,088.00

5.1

      Progress monitoring

1 day

Wed 24/08/22

Wed 24/08/22

Project manager

$520.00

5.2

      Stakeholders signoff

1 day

Thu 25/08/22

Thu 25/08/22

Project coordinator

$464.00

5.3

      collecting all warranty manuals

2 days

Fri 26/08/22

Mon 29/08/22

Senior system engineer

$880.00

5.4

      releasing resources

1 day

Fri 26/08/22

Fri 26/08/22

Azure engineer

$424.00

5.5

      Continuous improvement program

2 days

Fri 26/08/22

Mon 29/08/22

Senior network consultant

$800.00

5.6

      Milestone 5- Project closeout

0 days

Mon 29/08/22

Mon 29/08/22

$0.00

 

Figure 4: Resource graph for the project

(Source: created by author)

 

Figure 5: Cash flow chart

(Source: created by author)

Cost, time and quality are collaboratively known as triple constraint. Constraints are the limitation or boundary, that restricts project. In other words, for avoiding risks related to quality, cost and time, any project manager should consider triple constraints. The project success can be impacted by the cost, quality and time. Project manager should control the triple constraints through trade-offs. In project management, triple constraint is important because it helps to recognize competing demand in each project. For every project, the assigned project manager must decide the most essential demand. If any sudden changes occur, then the project team can easily adopt those changes with the help of triple constraints.

The triple constraints considered by the company X are quality, cost and time. These constraints can also be interpreted as budget, minimum performance and acceptance criteria and deadline. Proper analysis of the constraints is focused on benefits of affordability, maintainability, scalability and availability. Before considering the standards for knowledge areas, exact three areas of influence that are cost, time and quality must be considered. In order to gain competitive advantages and sustainable growth in IT service delivery all three constraint should be highlighted. Before preparing the knowledge management system effective feedback and adequate information should be available. For gathering information questionnaire has to be developed considering triple constraints.

Gantt Chart

After conducting interviews and gathering adequate information regarding time, cost and quality, it is determined that for this project quality is the most important constraint. Quality is defined as a knowledge area that ensures the project manager team is consistent and successful to deliver quality IT services to their customers. For both technical and business success quality is very essential. It not only satisfies the customers but the stakeholders as well. effective quality will reduce the probability of rework, higher the business efficient and productivity. Quality constraint can satisfy both the team and customers.

Alvarenga, J.C., Branco, R.R., do Valle, A.B., Soares, C.A.P. and e Silva, W.D.S., 2018. A revaluation of the criticality of the project manager to the project’s success. Business management dynamics, 8(2), p.1.

Hoffmann, D., Ahlemann, F. and Reining, S., 2020. Reconciling alignment, efficiency, and agility in IT project portfolio management: Recommendations based on a revelatory case study. International Journal of Project Management, 38(2), pp.124-136.

Kanabar, V., Hefley, W., Messikomer, C. and Thomas, A., 2016. Integrating Ethics and Professionalism Learning Outcomes in a Project Management Course.

Karabulut, M., 2017. Application of Monte Carlo simulation and PERT/CPM techniques in planning of construction projects: A Case Study. Periodicals of Engineering and Natural Sciences, 5(3).

Kavishe, N. and Chileshe, N., 2018. Identifying project management practices and principles for Public–Private partnerships in housing projects: The case of Tanzania. Sustainability, 10(12), p.4609.

Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kerzner, H., 2019. Using the project management maturity model: strategic planning for project management. John Wiley & Sons.

McGrath, S. K. and Whitty, S. J., 2020. What do project management practitioners think governance is? A study on perceptions in Queensland, Australia. International Journal of Managing Projects in Business.

Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), pp.169-179.

Sanchez, F. and et. al., 2020. An approach based on bayesian network for improving project management maturity: an application to reduce cost overrun risks in engineering projects. Computers in Industry, 119, p.103227.

Sanchez, O.P. and Terlizzi, M.A., 2017. Cost and time project management success factors for information systems development projects. International Journal of Project Management, 35(8), pp.1608-1626.

Shukla, S. and Kushwaha, N., 2020. Planning and Scheduling of a Suspension Cable Bridge Using Project Management Tool Primavera P6.

So?ta-Dr?czkowska, E. and Mro?ewski, M., 2020. Exploring the role of project management in product development of new technology-based firms. Project Management Journal, 51(3), pp.294-311.

Varajão, J., Colomo-Palacios, R. and Silva, H., 2017. ISO 21500: 2012 and PMBoK 5 processes in information systems project management. Computer Standards & Interfaces, 50, pp.216-222. 

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP