Project Management On RALS Rostering

Measurable Organizational Values

Discuss about the Project Management on RALS Rostering.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The B T and Sons Farming Equipments established the Riverina Agricultural and Lifestyle show in the year of 2000. Every year this show is arranged in November. The main target of this show is to display the local business, farmers, lifestyle products and agricultural equipment suppliers. The management department of RALS required to make coordination between the show stands, displays arranged in live programs, catering, volunteers and other specific requirements needed in any program. Previously the show did not have specific goals and objectives to be developed in the concerned scenario but after understanding their developmental requirements, they have grown to community committee. However, the Globex is still committed to RALS and maintain a strong community engagement with the help of strong and perfect management structure. The management mainly maintains the records relate to the donations, tickets and other specific arrangements required to organize a reprogram.

This report is elaborating a project related to the establishment a new rostering system within the RALS in order to improvise their rostering system that is not up to the mark according to their demands. This rostering system manages the all the operation of the volunteers of RALS. These operations are donation management, selling of tickets, cleaning of RAL sites that is messed up after nay program etc. Establishment of this rosteering system is required project plan in order to successfully be installed within RALS. This report is discussing the present scope and management plans for this project. This plan involves the technology and resources required for this project. in addition to this equipments and many important factors, this project require a structured project implementation schedule that will elaborate the specific process and their required timings. At the final stage of this project it will be elaborating the several risk factors associated with it, identification of which will to improvise the quality management of the system.

Measurable organization values are concerned with the goals and objectives of this project. The concerned goals and objectives of this project are to achieve the structured analysis of the organizational resources and system requirements that are necessary to develop the rostering system within RALS. In order to manage the project MOV procedure is followed and applied. This procedure is involves six steps within the system:

Recognition of the are impactful areas

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Cost analysis of the project

Scope Management Plan

Appropriate metric development required for the project

Time estimation for the completion of the project

Verification and agreement from the stakeholders involved within the project

Summarization of the values hidden in the project

Implementation of the project requires having the detailed information about their volunteers and their functionalities within the project with specific timing. This detailed information about the rank and timing schedule related to the volunteers are helpful while analyzing the project success as these factors will directly affect the project success.

Details of the Functionalities of the Volunteers

Rank

2

1

3

4

5

Areas of Impact

Strategies

Customer

Financial Details

Operation

Society

Value

A strategic step allows the RALS to achieve increase in shares. This also helps to innovate the services according to customer demands.

The rostering system makes the volunteers available to their concerned customers and improvises the service providence.

RALS can save money with the help of investing their money in the agricultural sector. This will make their share value high.

Evaluation of the organizational value helps to reduce the cost involved within the operational context.

Socital value addition to the operational context is helpful so as to obtain the accurate information

Metric

This is introduced within the system to increase the share value by 10 percent.

Rostering system saves more time than the manual process of recoding arranging programs.

Rostering system reduces the cost involved by 20 percent.

The customer satisfaction must be handled on first priority and the response time of the volunteer should be less.

Effective communication reduces the time taken for understanding the customer demands.

Time Required to complete each work

3 months

2 month

4 months

8 months

4 months

MOV procedure is introduced into the system in order to achieve the structured and effective system of operation within the rostering system. Management of the roles and segmented tasks among the volunteer becomes easy with the help of the MOV system within rostering system. These collections of information are guaranteed and accurate in comparison with the manual collection of data about the customers and new programs. Required timing for the manual error correction as well as error detection becomes easy to be solved. RALS information system becomes very strong and compatible with the evolving challenging environments.

Project Scope

All the private data and private responses collected from the volunteer and customer should be kept secured from any kind of threats, unauthorized access and malfunctioning of data. This aspect is very important in order to protect the organizational data safe from external harmful resources. The shared data between the administration and management or any higher authority of the organization must be kept secured with respect to the external environment. All of these above mentioned steps requires the entire manual set up within the organization to be replaced by the cloud based system, this aspect results into the protection of all the data as well as accuracy of the data will be maintained. This project should considers the all the required process within the set up. In addition to this, the volunteer should observe all the activities followed by their clients and administrators. Database administrator has to be used by RLSA in order to maintain the updated data every time. This updated data will help the manager to forward right data to their clients. This helps to fulfill all the demands of the clients. In addition to this, the entire system must be flexible with the changed structure of operations in order to achieve the most effective and dedicated system as a hole.

Roles and responsibilities of the developers in this project are as follows:

Roles

Responsibilities

Project Manager

The manager of the project has the responsibility to ensure a good growth with a structured way of completion to the project.

Project Sponsor

Project sponsors are responsible for the arranging the funds from market as well as from the partners of RALS.

Project scheduler

Scheduler decides the framework related to the structure of the project. He decides which part of the project has completed within a specific time span.

Risk Manager

The duty and responsibility of the risk manager is to manage the risk associated with the developmental process of the project and they have to analyze the resolution technique to resolve these risks.

Designer

Responsibility of a system designer is to arrange the outputs of the project according to the demands of the clients.

Analyst

Analyst finds the available resources for the project and helps to arrange these resources according to demands of the project.

Business Consultant

As per name, it is clear that the consultant have to develop the suggestions for the betterment of the concerned project. More specifically, they have to find out the flaws within the project.

Financial Manager

Financial manager is responsible for managing the expenses involved in the project.

Technology Applied

Technological tools and equipments are mainly used in the project in order to achieve the best outcome from the project. Among these several technological tools few are UML Techniques, database model tools, improvised and innovative programming languages and various library functions. These above technological tools can help in building a successful project structure in order to attain successful results. In addition to this, there several technical equipments that may be helpful in attaining the project goals and objectives: laptops, desktops, other technologically advanced equipments. Networking is another important aspect while considering the developmental perspective of the project. There is also several networking protocol available in the contemporary market that will help to make the structuring of the project possible. Grant chart, Pert chart are also helpful in identifying the detailed structure of the project.

New and technologically advanced system will requires a structured training facility. This training facility will be helpful in finding the solutions for the difficult situations at the time of the project development. The information entered in to the system is up to 2017, so about these data the employees should be trained properly.

Project Schedule

Task Mode

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Auto Scheduled

Riverina Rostering system development

180 days

Thu 9/22/16

Wed 5/31/17

   

Auto Scheduled

   Initialization phase

29 days

Thu 9/22/16

Tue 11/1/16

   

Auto Scheduled

      Development of the SRS document

15 days

Thu 9/22/16

Wed 10/12/16

 

Developer,Requirement analyst,project manager

Auto Scheduled

      Study of feasibility of the existing system

9 days

Thu 10/6/16

Tue 10/18/16

3

project manager,Requirement analyst,Developer,Risk manager

Auto Scheduled

      Requirement identification of the desired system

5 days

Mon 10/17/16

Fri 10/21/16

3,4

Requirement analyst,Developer

Auto Scheduled

      identification of the utility of the desired system

8 days

Mon 10/24/16

Wed 11/2/16

3,5

Developer,Requirement analyst,project manager,Risk manager

Auto Scheduled

      Meeting with the visitors and management heads

6 days

Mon 10/24/16

Mon 10/31/16

4,5

Accountant,Executive sponsor,project manager

Auto Scheduled

   Appointing of development vendor

21 days

Mon 10/31/16

Mon 11/28/16

   

Auto Scheduled

      Development vendor identification

6 days

Mon 10/31/16

Mon 11/7/16

5,7

Accountant, project manager,Developer,Requirement analyst

Auto Scheduled

      Analysis of the vendor capability and background

14 days

Mon 10/31/16

Thu 11/17/16

7

Developer,Executive sponsor,project manager,Requirement analyst

Auto Scheduled

      Plan of total time span reuired for completion

8 days

Mon 11/14/16

Wed 11/23/16

9,10

Developer,project manager,Software tester

Auto Scheduled

      Planning of the Budget

5 days

Wed 11/23/16

Tue 11/29/16

11,10

Accountant

Auto Scheduled

   Design Phase

38 days

Mon 11/14/16

Wed 1/4/17

   

Auto Scheduled

      Improvement of the Labour management

12 days

Mon 11/14/16

Tue 11/29/16

10

project manager,Executive sponsor,Risk manager

Auto Scheduled

      Begining of buiding the system

20 days

Mon 11/28/16

Fri 12/23/16

14

Developer,project manager,Requirement analyst

Auto Scheduled

      Improvisationof the installation process

6 days

Thu 12/22/16

Thu 12/29/16

11,15

Developer

Auto Scheduled

      Identifying the system requirements for next built

6 days

Thu 12/29/16

Thu 1/5/17

16

Developer,project manager,Requirement analyst

Auto Scheduled

   Milestone: Completion of design phase

0 days

Thu 9/22/16

Thu 9/22/16

   

Auto Scheduled

   Implementation phase of the system at organization

32 days

Thu 1/5/17

Fri 2/17/17

   

Auto Scheduled

      Implementation process according to the business objectives

12 days

Thu 1/5/17

Fri 1/20/17

17,18

Developer,project manager,Requirement analyst,Software tester

Auto Scheduled

      Modification required at the first stage of built

7 days

Thu 1/19/17

Fri 1/27/17

20

Developer,Requirement analyst,project manager,Risk manager

Auto Scheduled

      Collecting resources and elements

14 days

Thu 1/26/17

Tue 2/14/17

21

Accountant,project manager,Developer,Executive sponsor

Auto Scheduled

      Verification of the elements and resources

7 days

Mon 2/13/17

Tue 2/21/17

22

Developer,project manager,Requirement analyst

Auto Scheduled

   Testing phase

25 days

Mon 2/20/17

Fri 3/24/17

   

Auto Scheduled

      Prototyping of the system for test

8 days

Mon 2/20/17

Wed 3/1/17

22,23

Executive sponsor,project manager,Developer,Requirement analyst,Software tester

Auto Scheduled

      Process of the test plan

8 days

Wed 3/1/17

Fri 3/10/17

23,25

Software tester

Auto Scheduled

      Analysis of the test in real scenario

9 days

Mon 3/13/17

Thu 3/23/17

25,26

Risk manager,Software tester,Developer,project manager

Auto Scheduled

      Presentaion of the test results

2 days

Thu 3/23/17

Fri 3/24/17

25,27

project manager,Software tester,Developer,Risk manager

Auto Scheduled

   Milestone: acceptance of the test results by client

0 days

Thu 9/22/16

Thu 9/22/16

   

Auto Scheduled

   Risk management phase

24 days

Mon 3/27/17

Thu 4/27/17

   

Auto Scheduled

      Possible risk identification

8 days

Mon 3/27/17

Wed 4/5/17

28,29

Risk manager,Software tester,Developer

Auto Scheduled

      Presentation of the risk

3 days

Wed 4/5/17

Fri 4/7/17

31

project manager,Risk manager,Developer

Auto Scheduled

      Mitigation process of the risks

8 days

Wed 4/5/17

Fri 4/14/17

31

Developer,Risk manager,project manager

Auto Scheduled

      Registration of the impacts concerned with the risks

6 days

Fri 4/14/17

Fri 4/21/17

31,33

Developer,Risk manager,Software tester

Auto Scheduled

      Identification of the impacts of the riskss

15 days

Fri 4/7/17

Thu 4/27/17

32

project manager,Risk manager,Developer,Requirement analyst,Software tester

Auto Scheduled

   Milestone: Accepetance of the risk document by the client

0 days

Thu 9/22/16

Thu 9/22/16

   

Auto Scheduled

   Closure of the project

24 days

Fri 4/28/17

Wed 5/31/17

   

Auto Scheduled

      Measurement of the functionality of the developed system

10 days

Fri 4/28/17

Thu 5/11/17

35

Requirement analyst,project manager,Risk manager,Software tester

Auto Scheduled

      Roll out of the final developed project

15 days

Thu 5/11/17

Wed 5/31/17

38

Developer,project manager,Accountant,Requirement analyst,Risk manager

Auto Scheduled

   Milestone: Installation of the final system to the organization

0 days

Wed 5/31/17

Wed 5/31/17

39

 

Assumptions

This must have to be accepted that the project will be completed within the selected time span and estimated expense. In addition to this, it is assured that all the tasks related to the project will be under control and observation. All the members of the project are required to finish their task as per their scheduled timings. If all the tasks are finished in the scheduled timing then other colleagues are also not affected by the delay. Besides all of these aspects, this is also important that the supervisor checks all the operating measures according to the demands of the project. This will ensure the development of the rostering framework of RALS.

Identified Risks

Member associated with the Risk

Details

Mitigation Techniques

Technical Risks

System head

The entire set up of the project may face so many technical problems due to slow network or other technical disadvantages.

The monitoring of the servers and networks should be observed regularly. A Structured maintenance should be done in a regular interval of time.

Financial Risk

Financial Manager

Some situations introduce extra expense to the entire system set up. This aspect may leads to the shortage in budget plans of RALS.

Some extra money should be invested into the system in order to maintain the system in an emergency time.

Lack of Resources

Project Manager

Is the estimation of the project is not done properly in a correct way then the entire project may disrupted. As a result of this the progress of the project may get delayed.

Estimation of the tools and resources that are not present in the system should be analyzed in proper point of time.

Loss of Manpower

Project Manager

There are so many perspectives that consider the reduce in work force in the project management. The members may got ill or there may be any other kind of problems within the system.

Some extra team members should always be ready in order to do provide extra work at the time of pressure.

Risk in Privacy

Project Manager

The data collected from the volunteers must be kept privately and in a secured way.

The signature and other important factors should be made secured within the system.

Project Name: RALS Rostering Project

Project Manager Name

Type

Reason

Time Taken

Owner

Method

Status

Authorization of Expense

The authorization related to the expense of the development of the project should be centered in the hand of a single person.

3 months

Financial Manager

Management of expense

Open

Documentation related to project

The documentation of the project must be done regularly.

2 Months

Project Manager

Monitoring of Project progress

Closed

Work Break Down Structure

This system specifies the task assigned to each member of the project.

3 months

Project Manager

Providing inspiration to the project development team

Open

Plan of the Project

According to the requirements of the clients analysis of the project is done

1 month

Project Manager

Monitoring measures of the project for any kind of risks to be found

Closed

Plan of the Risk

Risks within the project must be analyzed for making the development of the project smooth

2 months

Risk Manager

Review framework of the project

Open

MOV

Stakeholder associated with the project is identified with the help of this aspect

3 months

Project Manager

Observing

Closed

Material required for Training

Training schedule and manual is provided to the team members in order to improve their efficiency

3 months

Project Manager

Journals and Presentations

Open

Conclusion

This report can conclude that the RALS have arranged a set of activities that will helps to make a management system replacing their manual system of operation and also reduce the dependency on their volunteer. The new system will provide an automated system set up to RALS that will make them more efficient in the field o arranging programs and managing their customer demands. All the required elements for this project implementation and planning are described in this report. In addition to this all the risk factors and risk resolution steps are also discussed in this report with the individual roles of the project member in risk resolving measures. This entire proposed system will reduces the excess pressure on the staffs and will help the managers to gain good amount of revenues in comparison with their competitors. In addition to this, this entire project not only elaborated the project details, but also it has elaborated the roles and functionalities of the project members. The new rostering system of RALS will be more efficient than the conventional manual operating system followed by them.

Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.

Burke, R. (2013). Project management: planning and control techniques.New Jersey, USA.

Chia, R. (2013). Paradigms and perspectives in organizational project management research: implications for knowledge creation. Novel Approaches to Organizational Project Management Research: Translational and Transformational. Copenhagen Business School Press, Copenhagen, 33-55.

Gido, J., & Clements, J. P. (2014). Successful project management. Nelson Education.

Grefen, P., Pernici, B., & Sánchez, G. (Eds.). (2012). Database support for workflow management: the WIDE project (Vol. 491). Springer Science & Business Media.

Heagney, J. (2012). Fundamentals of project management. AMACOM Div American Mgmt Assn.

Heagney, J. (2012). Fundamentals of project management. AMACOM Div American Mgmt Assn.

Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Leach, L. P. (2014). Critical chain project management. Artech House.

Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Steyn, H., Dekker, A. H., Kuschke, B., Van Eck, B. P. S., & Visser, K. (2016). Project management: A multi-disciplinary approach.

Steyn, H., Dekker, A. H., Kuschke, B., Van Eck, B. P. S., & Visser, K. (2016). Project management: A multi-disciplinary approach.

Turner, R. (2016). Gower handbook of project management. Routledge.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.

Walker, A. (2015). Project management in construction. John Wiley & Sons.

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now