Discuss about the Information Systems Project Management.
Project management can be described as a set of practices those could be accomplished in a sequential manner that can lead to a successful daily operational activity or a big project. The project charter has been presented considering the aspects and activities necessary for the accomplishment of the chosen case study, which is a connected city ‘connect regionally and globally.’ This project charter explains the constraints those could be utilized for the development of project planning and executing a successful project that will be helpful in developing a transport network for allowing the consumers to be connected with the major cities and global world.
The purpose of this report is to explain the aspects of the project management those are necessary for the successful deployment of the project a connected city in an efficient and effective manner. This report presents the schedule, cost, activities, and risks associated with the delivery of this project.
The project will provide a transport network for the individuals of the Melbourne city to be connected by road with the Australia’s major cities and Asian-pacific regions around the world. Latest technologies will be utilized for allowing the implementation of this project in an efficient and effective manner. Sensors and GPS tracking system will be incorporated within the transport vehicles.
The changes will be applied within the Melbourne city only and the boundaries of the transportation and logistics services will be altered within the Australia. This project will allow the Melbourne city to be connected with the world and allowing the individuals to avail better and enhanced transport services. The project has been expected to be completed within 613 days in around a budget $ $2,552,800.00. The legal authorities and expenses on the technology have been out of scope for this project. The establishment has been estimated to being established within the Melbourne City only, connectivity and network of the outside world has been out of scope. Security aspects are out of scope for this project charter.
Primary requirement will be the experienced leadership and managerial qualities for leading the project towards the success. The airports will have connectivity with the global cities and major cities of the Australia for which legal agreements will be necessary for allowing the airplanes to fly above their land. The human resources required for the project are project manager, market analyst, resource manager, contractors, human labors, and material resources necessary for the development of the project successfully.
Cost escalation: Budget of the project might increase due to certain uncertainties.
Schedule escalation: Schedule of the project might increase due to certain uncertainties.
Resource lagging: If not managed properly, the resource lagging can occur
Resource Jumping: Utilization of resources more than the application is another issue in this project
Internal conflicts: since, the project will be a long duration project and thus, there are the possibilities that the conflict occur within the project stakeholders
Considerable objectives for the project can be described as follows
Task Name |
Duration |
Start |
Finish |
A connected City |
613 days |
Thu 5/17/18 |
Mon 9/21/20 |
Phase 1: Planning |
225 days |
Thu 5/17/18 |
Wed 3/27/19 |
Phase 1 completed |
0 days |
Wed 3/27/19 |
Wed 3/27/19 |
Phase 2: project execution |
200 days |
Thu 3/28/19 |
Wed 1/1/20 |
Phase 2 completed |
0 days |
Wed 1/1/20 |
Wed 1/1/20 |
Phase 3: Monitoring and Auditing |
103 days |
Thu 1/2/20 |
Mon 5/25/20 |
Phase 3 completed |
0 days |
Mon 5/25/20 |
Mon 5/25/20 |
Phase 4: Project Closure |
85 days |
Tue 5/26/20 |
Mon 9/21/20 |
Project closure completed |
0 days |
Mon 9/21/20 |
Mon 9/21/20 |
WBS |
Task Name |
Finish |
Resource Names |
Cost |
1 |
A connected City |
Wed 1/1/20 |
$2,363,600.00 |
|
1.1 |
Phase 1: Planning |
Wed 3/27/19 |
$682,400.00 |
|
1.1.1 |
Analyzing problem |
Mon 6/18/18 |
$0.00 |
|
1.1.2 |
Defining the problem statement |
Mon 7/16/18 |
Business Analyst, Human resource, Project manager |
$104,000.00 |
1.1.3 |
Airways network for establishing the network |
Wed 8/15/18 |
Business Analyst, Human resource, Project manager |
$114,400.00 |
1.1.4 |
feasibility analysis |
Wed 9/19/18 |
Business Analyst, Human resource, Project manager |
$130,000.00 |
1.1.5 |
Preparing project charter |
Wed 10/17/18 |
Business Analyst, Human resource, Project manager |
$104,000.00 |
1.1.6 |
Scope |
Tue 11/20/18 |
Executives, Project manager |
$48,000.00 |
1.1.7 |
budget |
Tue 12/25/18 |
Executives, Project manager |
$50,000.00 |
1.1.8 |
Schedule |
Thu 1/24/19 |
Executives, Project manager |
$44,000.00 |
1.1.9 |
Deliverables |
Wed 2/20/19 |
Executives, Project manager |
$38,000.00 |
1.1.10 |
Risks |
Wed 3/27/19 |
Executives, Project manager |
$50,000.00 |
1.1.11 |
Phase 1 completed |
Wed 3/27/19 |
Executives, Project manager |
$0.00 |
1.2 |
Phase 2: project execution |
Wed 1/1/20 |
$874,800.00 |
|
1.2.1 |
Stakeholders roles and responsibilities |
Tue 6/4/19 |
Project manager, Executives |
$98,000.00 |
1.2.2 |
work breakdown structure |
Fri 7/5/19 |
Project manager, Resource manager |
$64,400.00 |
1.2.3 |
New airport constructions |
Fri 9/13/19 |
Project manager, Resource manager, Architecture, Human resource |
$240,000.00 |
1.2.4 |
implementing GPS |
Tue 10/22/19 |
Project manager, Resource manager, Architecture, Human resource |
$129,600.00 |
1.2.5 |
Connecting via road |
Fri 11/29/19 |
Human resource, IT team, Resource manager, resources[1] |
$178,400.00 |
1.2.6 |
incorporating registrations |
Wed 1/1/20 |
Human resource, IT team, Resource manager, resources[1] |
$164,400.00 |
1.2.8 |
Phase 2 completed |
Thu 5/17/18 |
Human resource, IT team, Resource manager, resources[0] |
$0.00 |
1.3 |
Phase 3: Monitoring and Auditing |
Mon 10/8/18 |
$432,400.00 |
|
1.3.1 |
Real world application |
Wed 6/6/18 |
Business Analyst, Executives, IT team, Project manager |
$60,000.00 |
1.3.2 |
Identification of issues |
Mon 7/2/18 |
Business Analyst, Executives, IT team, Project manager |
$72,000.00 |
1.3.3 |
Management of the changes |
Fri 7/27/18 |
Business Analyst, Executives, IT team, Project manager |
$76,000.00 |
1.3.4 |
Changes idetification |
Fri 8/17/18 |
Business Analyst, Project manager, Resource manager |
$66,000.00 |
1.3.5 |
Implementing changes |
Mon 10/8/18 |
Business Analyst, Project manager, Resource manager |
$158,400.00 |
1.3.6 |
Phase 3 completed |
Mon 10/8/18 |
Business Analyst, Project manager, Resource manager |
$0.00 |
1.4 |
Phase 4: Project Closure |
Mon 2/4/19 |
$374,000.00 |
|
1.4.1 |
Documentation |
Mon 11/19/18 |
Business Analyst, Executives, Project manager, Resource manager |
$132,000.00 |
1.4.2 |
sign-off |
Mon 12/17/18 |
Business Analyst, Executives, Project manager, Resource manager |
$88,000.00 |
1.4.3 |
lessons learned documentation |
Mon 1/14/19 |
Business Analyst, Executives, Project manager, Resource manager |
$88,000.00 |
1.4.4 |
releasing resources |
Mon 2/4/19 |
Business Analyst, Executives, Project manager, Resource manager |
$66,000.00 |
1.4.5 |
Project closure completed |
Mon 2/4/19 |
Business Analyst, Executives, Project manager, Resource manager |
$0.00 |
Stakeholders |
Responsibilities |
Roles |
Impact |
Interest |
Project Manager |
Accomplish the project constraints |
Manage the project activities |
Very High |
Very High |
Project Sponsor |
Provide necessary funds |
Provide funds |
Low |
Very High |
IT Architect |
Present a sophisticated model |
Establish hardware and configuration |
Medium |
High |
Business Analyst |
Market research |
Analyze the needs market |
Medium |
Medium |
Government |
Support legally |
Allow for the establishment |
Very High |
Medium |
Common Citizens of Australia |
Provide feedback |
Avail the services |
Very High |
Very High |
IT technicians |
Accomplish their roles |
Implement the technologies |
Low |
Low |
Conclusion
Following the above planning and activities could be helpful in establishing the transport and logistic network globally and major cities of the Australia. Based on the above report it can be concluded that the project can be accomplished in an efficient and effective manner of the above mentioned activities has been accomplished within the prosed planning. This is a bigger project and so the project would be completed in 613 days with a total expense of $ 2,413.600.
Brooks, R., 2015. Financial management: core concepts. Pearson.
Crawford, J.K., 2014. Project management maturity model. CRC Press.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Gido, J., Clements, J. and Clements, J., 2014. Successful project management. Nelson Education.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.
Olson, D., 2014. Information systems project management. Business Expert Press.
We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.
Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.
Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.
Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.
Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.
Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.
We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.
Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.
You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.
Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.
Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.
You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.
You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.
Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.
We create perfect papers according to the guidelines.
We seamlessly edit out errors from your papers.
We thoroughly read your final draft to identify errors.
Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!
Dedication. Quality. Commitment. Punctuality
Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.
We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.
We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.
We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.
We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.