In this homework assignment, you will be
working through two crashing problems and four earned value problems. All the
information you need is included within this Homework packet. Make sure you
answer all parts of the questions in their entirety.
Once you have worked through the
problems, please post your responses to the Drop Box. Please refer to the
course syllabus for the due date.
PROBLEM
1
Use the network diagram below and the
additional information provided to answer the corresponding questions. [15
points]
.jpg” alt=”Crashing network 1″>
a) The crash cost per day per activity.
[10 points]
b) Which activities should be crashed to
meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these
activities? [3 points]
c) Find the new budget (or cost of the
project). [2 points]
PROBLEM
2
Use the network diagram below and the
additional information provided to answer the corresponding questions. [13
points]
.jpg” alt=”Crashing network 2″>
a) The crash cost per day per activity.
[10 points]
b) Which activities should be crashed to
meet a project deadline of 13 days at minimum cost? What is the cost impact of
crashing these activities? [3 points]
PROBLEM
3 [8 points]
Month
ACWP
BCWS
BCWP
22
$540
$523
$535
a) Calculate
the CV (Cost Variance). [2 points]
b) Is
the CV over or under budget? [2 points]
c) Calculate
the SV (Schedule Variance). [2 points]
d) Is
the SV ahead or behind schedule? [2 points]
PROBLEM
4 [8 points]
Month
ACWP
BCWS
BCWP
5
$34
$42
$39
a) Calculate
the CPI (Cost Performance Index). [2 points]
b) Is
the project cost efficient or not efficient? [2 point]
c) Calculate
the SPI (Schedule Performance Index) [2 points]
d) Is
the schedule efficient or not efficient? [2 point]
PROBLEM
5 [8 points]
Day
ACWP
BCWS
BCWP
65
$550
$735
$678
a) Calculate
the CV (Cost Variance). [2 points]
b) Calculate
the CPI (Cost Performance Index). [2 points]
c) Calculate
the SV (Schedule Variance). [2 points]
d) Calculate
the SPI (Schedule Performance Index) [2 points]
PROBLEM
6 [8 points]
Day
ACWP
BCWS
BCWP
65
$750
$735
$678
a) Calculate
the CV (Cost Variance). [1 point]
b) Calculate
the CPI (Cost Performance Index). [1 point]
c) Calculate
the SV (Schedule Variance). [1 point]
d) Calculate
the SPI (Schedule Performance Index) [1 points]
e) Explain
the project performance in terms of efficiency, budget and schedule. What
should the project manager do for the project? [4 points]
We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.
Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.
Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.
Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.
Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.
Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.
We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.
Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.
You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.
Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.
Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.
You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.
You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.
Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.
We create perfect papers according to the guidelines.
We seamlessly edit out errors from your papers.
We thoroughly read your final draft to identify errors.
Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!
Dedication. Quality. Commitment. Punctuality
Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.
We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.
We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.
We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.
We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.