Planning And Construction Of Boarding Houses In NSW

Question:
Discuss about the Planning And Construction Of Boarding Houses In NSW.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
 
Answer:
Introduction

This project is based on the development of rental residential buildings (including several housing / boarding units) in Newcastle, NSW. The proposed project is proposed to be completed in a period of the next two years within a feasible budget investment. In addition to the proposed plan of the boarding units, there are several other specifications that are required to be met in the project. These specifications include the placement of the rooms inside the building units, number of floors, facilities and services, parking areas and others. For executing the project, all these requirements are to be met and based on the requirements, a suitable budget and schedule plan is to be developed.

In this report, with the help of the analysis of the project requirements, a suitable work breakdown structure has been developed that includes the work specifications in each phase of the project along with the proposed durations and related costs in each of the work packages.

Project Scope and Objectives

The main scope of the project is to clear a certain piece of property and build 27 boarding units that will be provided as rentals. The scope statement of the project is defined by the following points.

  • Clearing of the entire land property for constructing the housing units is within the scope of the project.
  • Constructing the foundations of the buildings is within the scope of the project.
  • Building of the framework of the buildings is within the scope of the project.
  • Development of the buildings as well as their utilities and services is within the scope of the project.
  • Development of external utilities and perimeter walls is within the scope of the project.

From the scope statement, the project objectives are determined as follows.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
  • To survey the entire land and take measurements
  • To clear the land and prepare it for the construction
  • To build foundations of the buildings
  • To build 27 housing units including all the design specifications as provided earlier
  • To install utilities like electrical and drainage systems in each of the units
  • To hand over the finished project to the authority
 

The work breakdown structure of the project is shown in the following table.

WBS

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Cost

1

Site Preparation

80 days

Mon 5/28/18

Fri 9/14/18

   

$888,000.00

1.1

   Survey of the Entire Site

10 days

Mon 5/28/18

Fri 6/8/18

 

Construction Manager, Project Supervisor

$44,000.00

1.2

   Take Measurements of the Site

5 days

Mon 6/11/18

Fri 6/15/18

2

Construction Manager

$10,000.00

1.3

   Assign Workers to Prepare the Site

5 days

Mon 6/18/18

Fri 6/22/18

3

Construction Manager

$10,000.00

1.4

   Allocate Resources for Site Preparation

5 days

Mon 6/25/18

Fri 6/29/18

4

Procurement Manager

$6,000.00

1.5

   Hire Equipments for Site Preparation

15 days

Mon 7/2/18

Fri 7/20/18

5

Procurement Manager

$18,000.00

1.6

   Start Preparing the Selected Site

5 days

Mon 7/23/18

Fri 7/27/18

6

Construction Workers

$100,000.00

1.7

   Start Digging of the Land

10 days

Mon 7/30/18

Fri 8/10/18

7

Construction Workers

$200,000.00

1.8

   Remove Existing Plants and Grasses

5 days

Mon 8/13/18

Fri 8/17/18

8

Construction Workers

$100,000.00

1.9

   Remove Existing Concrete Structures and Walls if Any

5 days

Mon 8/20/18

Fri 8/24/18

9

Construction Workers

$100,000.00

1.10

   Check Soil Quality

5 days

Mon 8/27/18

Fri 8/31/18

10

Construction Workers

$100,000.00

1.11

   Add Strong Soil

5 days

Mon 9/3/18

Fri 9/7/18

11

Construction Workers

$100,000.00

1.12

   Preparation of Foundation

5 days

Mon 9/10/18

Fri 9/14/18

12

Construction Workers

$100,000.00

2

Foundation

65 days

Mon 9/17/18

Fri 12/14/18

   

$1,300,000.00

2.1

   Complete Digging the Site

10 days

Mon 9/17/18

Fri 9/28/18

13

Construction Workers

$200,000.00

2.2

   Place Concrete Structures inside the Area

10 days

Mon 10/1/18

Fri 10/12/18

15

Construction Workers

$200,000.00

2.3

   Build Foundation

15 days

Mon 10/15/18

Fri 11/2/18

16

Construction Workers

$300,000.00

2.4

   Install Foundation Support

15 days

Mon 11/5/18

Fri 11/23/18

17

Construction Workers

$300,000.00

2.5

   Strengthen Foundation

10 days

Mon 11/26/18

Fri 12/7/18

18

Construction Workers

$200,000.00

2.6

   Fill Rest of Area with Soil

5 days

Mon 12/10/18

Fri 12/14/18

19

Construction Workers

$100,000.00

3

Structure

165 days

Mon 12/17/18

Fri 8/2/19

   

$3,300,000.00

3.1

   Start Building the Structure

5 days

Mon 12/17/18

Fri 12/21/18

20

Construction Workers

$100,000.00

3.2

   Procure Building Materials

5 days

Mon 12/24/18

Fri 12/28/18

22

Construction Workers

$100,000.00

3.3

   Hire Construction Equipments

5 days

Mon 12/31/18

Fri 1/4/19

23

Construction Workers

$100,000.00

3.4

   Hire Construction Workers

5 days

Mon 1/7/19

Fri 1/11/19

24

Construction Workers

$100,000.00

3.5

   Set Up Construction Camp

10 days

Mon 1/14/19

Fri 1/25/19

25

Construction Workers

$200,000.00

3.6

   Start Building the Infrastructures

20 days

Mon 1/28/19

Fri 2/22/19

26

Construction Workers

$400,000.00

3.7

   Install Steel Bars

15 days

Mon 2/25/19

Fri 3/15/19

27

Construction Workers

$300,000.00

3.8

   Place Bricks Along the Framework

25 days

Mon 3/18/19

Fri 4/19/19

28

Construction Workers

$500,000.00

3.9

   Apply Concrete to Fix the Bricks

25 days

Mon 4/22/19

Fri 5/24/19

29

Construction Workers

$500,000.00

3.10

   Place Concrete Layer on Inner and Outer Layers of the Walls

30 days

Mon 5/27/19

Fri 7/5/19

30

Construction Workers

$600,000.00

3.11

   Apply Plaster On the Walls

20 days

Mon 7/8/19

Fri 8/2/19

31

Construction Workers

$400,000.00

4

Services

90 days

Mon 8/5/19

Fri 12/6/19

   

$360,000.00

4.1

   Install Electrical Connections through Every Wall of the Housing Units

15 days

Mon 8/5/19

Fri 8/23/19

32

Technical Workers

$60,000.00

4.2

   Install Water Pipes and Plumbing Works

15 days

Mon 8/26/19

Fri 9/13/19

34

Technical Workers

$60,000.00

4.3

   Connect to Main Lines

5 days

Mon 9/16/19

Fri 9/20/19

35

Technical Workers

$20,000.00

4.4

   Install Water Tanks

15 days

Mon 9/23/19

Fri 10/11/19

36

Technical Workers

$60,000.00

4.5

   Build Elevator Boxes

20 days

Mon 10/14/19

Fri 11/8/19

37

Technical Workers

$80,000.00

4.6

   Install Elevators

20 days

Mon 11/11/19

Fri 12/6/19

38

Technical Workers

$80,000.00

5

Internal Finishes

40 days

Mon 12/9/19

Fri 1/31/20

   

$800,000.00

5.1

   Cut Door and Window Areas

5 days

Mon 12/9/19

Fri 12/13/19

39

Construction Workers

$100,000.00

5.2

   Build Door Frames

5 days

Mon 12/16/19

Fri 12/20/19

41

Construction Workers

$100,000.00

5.3

   Build Window Frames

5 days

Mon 12/23/19

Fri 12/27/19

42

Construction Workers

$100,000.00

5.4

   Install Doors

5 days

Mon 12/30/19

Fri 1/3/20

43

Construction Workers

$100,000.00

5.5

   Install Windows

5 days

Mon 1/6/20

Fri 1/10/20

44

Construction Workers

$100,000.00

5.6

   Install Switch Boxes and Plugs

5 days

Mon 1/13/20

Fri 1/17/20

45

Construction Workers

$100,000.00

5.7

   Install Electric Meters and Pumping Motor

5 days

Mon 1/20/20

Fri 1/24/20

46

Construction Workers

$100,000.00

5.8

   Apply Colours on Internal Walls

5 days

Mon 1/27/20

Fri 1/31/20

47

Construction Workers

$100,000.00

6

External Finishes

20 days

Mon 2/3/20

Fri 2/28/20

   

$400,000.00

6.1

   Apply Colours on External Walls

5 days

Mon 2/3/20

Fri 2/7/20

48

Construction Workers

$100,000.00

6.2

   Apply Designs

5 days

Mon 2/10/20

Fri 2/14/20

50

Construction Workers

$100,000.00

6.3

   Paint Names of Each Boarding House

5 days

Mon 2/17/20

Fri 2/21/20

51

Construction Workers

$100,000.00

6.4

   Build Shades on Windows

5 days

Mon 2/24/20

Fri 2/28/20

52

Construction Workers

$100,000.00

7

External Works

75 days

Mon 3/2/20

Fri 6/12/20

   

$1,800,000.00

7.1

   Connect Water Tank with Water Line

10 days

Mon 3/2/20

Fri 3/13/20

53

Construction Workers, Technical Workers

$240,000.00

7.2

   Connect Electrical Lines with Main Line

10 days

Mon 3/16/20

Fri 3/27/20

55

Construction Workers, Technical Workers

$240,000.00

7.3

   Build Perimeter Walls

15 days

Mon 3/30/20

Fri 4/17/20

56

Construction Workers, Technical Workers

$360,000.00

7.4

   Build Garden Space

5 days

Mon 4/20/20

Fri 4/24/20

57

Construction Workers, Technical Workers

$120,000.00

7.5

   Build a Swimming Pool

20 days

Mon 4/27/20

Fri 5/22/20

58

Construction Workers, Technical Workers

$480,000.00

7.6

   Build a Leisure Area

5 days

Mon 5/25/20

Fri 5/29/20

59

Construction Workers, Technical Workers

$120,000.00

7.7

   Finishing Touches

10 days

Mon 6/1/20

Fri 6/12/20

60

Construction Workers, Technical Workers

$240,000.00

Figure 1: Work Breakdown Structure of the Project

(Source: Created by Author)

The human resources that have been allocated to each of the work packages of the work breakdown structure are shown in the following table.

Resource Name

Type

Max. Units

Std. Rate

Ovt. Rate

Cost/Use

Accrue At

Base Calendar

Construction Manager

Work

100%

$250.00/hr

$0.00/hr

$0.00

Prorated

Standard

Project Supervisor

Work

100%

$300.00/hr

$0.00/hr

$0.00

Prorated

Standard

Construction Workers

Work

100%

$2,500.00/hr

$0.00/hr

$0.00

Prorated

Standard

Procurement Manager

Work

100%

$150.00/hr

$0.00/hr

$0.00

Prorated

Standard

Technical Workers

Work

100%

$500.00/hr

$0.00/hr

$0.00

Prorated

Standard

Conclusion

This report contains the details of the project scope, objectives and the overall work breakdown structure that will be followed. The work breakdown structure has been developed by dividing the entire project into several phases, sub-phases and work packages. As per the development, the work packages have been linked together using predecessor relationship as appropriate in the context of the project. The links between the work packages of the work breakdown structure are essential in determining the durations of each of the work packages. From the work breakdown structure provided above, the estimated duration for the project is 535 days and the estimated budget is $8,848,000. However, these are only preliminary estimations and will be changed in the near future in order to adjust with the project feasibility and the limitations the organization which is undertaking this particular project.

 
Bibliography

Banihashemi, S., Hosseini, M.R., Golizadeh, H. and Sankaran, S., 2017. Critical success factors (CSFs) for integration of sustainability into construction project management practices in developing countries. International Journal of Project Management, 35(6), pp.1103-1119.

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Nasir, N., Nawi, M.N.M. and Radzuan, K., 2016, August. Relationship between time management in construction industry and project management performance. In AIP Conference Proceedings (Vol. 1761, No. 1, p. 020079). AIP Publishing.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction project management. John Wiley & Sons.

Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming psychological safety climate in construction project management. International journal of project management, 33(1), pp.223-235.

Walker, A., 2015. Project management in construction. John Wiley & Sons.

Zheng, X., Le, Y., Chan, A.P., Hu, Y. and Li, Y., 2016. Review of the application of social network analysis (SNA) in construction project management research. International journal of project management, 34(7), pp.1214-1225.

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP