This project is based on the development of rental residential buildings (including several housing / boarding units) in Newcastle, NSW. The proposed project is proposed to be completed in a period of the next two years within a feasible budget investment. In addition to the proposed plan of the boarding units, there are several other specifications that are required to be met in the project. These specifications include the placement of the rooms inside the building units, number of floors, facilities and services, parking areas and others. For executing the project, all these requirements are to be met and based on the requirements, a suitable budget and schedule plan is to be developed.
In this report, with the help of the analysis of the project requirements, a suitable work breakdown structure has been developed that includes the work specifications in each phase of the project along with the proposed durations and related costs in each of the work packages.
The main scope of the project is to clear a certain piece of property and build 27 boarding units that will be provided as rentals. The scope statement of the project is defined by the following points.
From the scope statement, the project objectives are determined as follows.
The work breakdown structure of the project is shown in the following table.
WBS |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
1 |
Site Preparation |
80 days |
Mon 5/28/18 |
Fri 9/14/18 |
$888,000.00 |
||
1.1 |
Survey of the Entire Site |
10 days |
Mon 5/28/18 |
Fri 6/8/18 |
Construction Manager, Project Supervisor |
$44,000.00 |
|
1.2 |
Take Measurements of the Site |
5 days |
Mon 6/11/18 |
Fri 6/15/18 |
2 |
Construction Manager |
$10,000.00 |
1.3 |
Assign Workers to Prepare the Site |
5 days |
Mon 6/18/18 |
Fri 6/22/18 |
3 |
Construction Manager |
$10,000.00 |
1.4 |
Allocate Resources for Site Preparation |
5 days |
Mon 6/25/18 |
Fri 6/29/18 |
4 |
Procurement Manager |
$6,000.00 |
1.5 |
Hire Equipments for Site Preparation |
15 days |
Mon 7/2/18 |
Fri 7/20/18 |
5 |
Procurement Manager |
$18,000.00 |
1.6 |
Start Preparing the Selected Site |
5 days |
Mon 7/23/18 |
Fri 7/27/18 |
6 |
Construction Workers |
$100,000.00 |
1.7 |
Start Digging of the Land |
10 days |
Mon 7/30/18 |
Fri 8/10/18 |
7 |
Construction Workers |
$200,000.00 |
1.8 |
Remove Existing Plants and Grasses |
5 days |
Mon 8/13/18 |
Fri 8/17/18 |
8 |
Construction Workers |
$100,000.00 |
1.9 |
Remove Existing Concrete Structures and Walls if Any |
5 days |
Mon 8/20/18 |
Fri 8/24/18 |
9 |
Construction Workers |
$100,000.00 |
1.10 |
Check Soil Quality |
5 days |
Mon 8/27/18 |
Fri 8/31/18 |
10 |
Construction Workers |
$100,000.00 |
1.11 |
Add Strong Soil |
5 days |
Mon 9/3/18 |
Fri 9/7/18 |
11 |
Construction Workers |
$100,000.00 |
1.12 |
Preparation of Foundation |
5 days |
Mon 9/10/18 |
Fri 9/14/18 |
12 |
Construction Workers |
$100,000.00 |
2 |
Foundation |
65 days |
Mon 9/17/18 |
Fri 12/14/18 |
$1,300,000.00 |
||
2.1 |
Complete Digging the Site |
10 days |
Mon 9/17/18 |
Fri 9/28/18 |
13 |
Construction Workers |
$200,000.00 |
2.2 |
Place Concrete Structures inside the Area |
10 days |
Mon 10/1/18 |
Fri 10/12/18 |
15 |
Construction Workers |
$200,000.00 |
2.3 |
Build Foundation |
15 days |
Mon 10/15/18 |
Fri 11/2/18 |
16 |
Construction Workers |
$300,000.00 |
2.4 |
Install Foundation Support |
15 days |
Mon 11/5/18 |
Fri 11/23/18 |
17 |
Construction Workers |
$300,000.00 |
2.5 |
Strengthen Foundation |
10 days |
Mon 11/26/18 |
Fri 12/7/18 |
18 |
Construction Workers |
$200,000.00 |
2.6 |
Fill Rest of Area with Soil |
5 days |
Mon 12/10/18 |
Fri 12/14/18 |
19 |
Construction Workers |
$100,000.00 |
3 |
Structure |
165 days |
Mon 12/17/18 |
Fri 8/2/19 |
$3,300,000.00 |
||
3.1 |
Start Building the Structure |
5 days |
Mon 12/17/18 |
Fri 12/21/18 |
20 |
Construction Workers |
$100,000.00 |
3.2 |
Procure Building Materials |
5 days |
Mon 12/24/18 |
Fri 12/28/18 |
22 |
Construction Workers |
$100,000.00 |
3.3 |
Hire Construction Equipments |
5 days |
Mon 12/31/18 |
Fri 1/4/19 |
23 |
Construction Workers |
$100,000.00 |
3.4 |
Hire Construction Workers |
5 days |
Mon 1/7/19 |
Fri 1/11/19 |
24 |
Construction Workers |
$100,000.00 |
3.5 |
Set Up Construction Camp |
10 days |
Mon 1/14/19 |
Fri 1/25/19 |
25 |
Construction Workers |
$200,000.00 |
3.6 |
Start Building the Infrastructures |
20 days |
Mon 1/28/19 |
Fri 2/22/19 |
26 |
Construction Workers |
$400,000.00 |
3.7 |
Install Steel Bars |
15 days |
Mon 2/25/19 |
Fri 3/15/19 |
27 |
Construction Workers |
$300,000.00 |
3.8 |
Place Bricks Along the Framework |
25 days |
Mon 3/18/19 |
Fri 4/19/19 |
28 |
Construction Workers |
$500,000.00 |
3.9 |
Apply Concrete to Fix the Bricks |
25 days |
Mon 4/22/19 |
Fri 5/24/19 |
29 |
Construction Workers |
$500,000.00 |
3.10 |
Place Concrete Layer on Inner and Outer Layers of the Walls |
30 days |
Mon 5/27/19 |
Fri 7/5/19 |
30 |
Construction Workers |
$600,000.00 |
3.11 |
Apply Plaster On the Walls |
20 days |
Mon 7/8/19 |
Fri 8/2/19 |
31 |
Construction Workers |
$400,000.00 |
4 |
Services |
90 days |
Mon 8/5/19 |
Fri 12/6/19 |
$360,000.00 |
||
4.1 |
Install Electrical Connections through Every Wall of the Housing Units |
15 days |
Mon 8/5/19 |
Fri 8/23/19 |
32 |
Technical Workers |
$60,000.00 |
4.2 |
Install Water Pipes and Plumbing Works |
15 days |
Mon 8/26/19 |
Fri 9/13/19 |
34 |
Technical Workers |
$60,000.00 |
4.3 |
Connect to Main Lines |
5 days |
Mon 9/16/19 |
Fri 9/20/19 |
35 |
Technical Workers |
$20,000.00 |
4.4 |
Install Water Tanks |
15 days |
Mon 9/23/19 |
Fri 10/11/19 |
36 |
Technical Workers |
$60,000.00 |
4.5 |
Build Elevator Boxes |
20 days |
Mon 10/14/19 |
Fri 11/8/19 |
37 |
Technical Workers |
$80,000.00 |
4.6 |
Install Elevators |
20 days |
Mon 11/11/19 |
Fri 12/6/19 |
38 |
Technical Workers |
$80,000.00 |
5 |
Internal Finishes |
40 days |
Mon 12/9/19 |
Fri 1/31/20 |
$800,000.00 |
||
5.1 |
Cut Door and Window Areas |
5 days |
Mon 12/9/19 |
Fri 12/13/19 |
39 |
Construction Workers |
$100,000.00 |
5.2 |
Build Door Frames |
5 days |
Mon 12/16/19 |
Fri 12/20/19 |
41 |
Construction Workers |
$100,000.00 |
5.3 |
Build Window Frames |
5 days |
Mon 12/23/19 |
Fri 12/27/19 |
42 |
Construction Workers |
$100,000.00 |
5.4 |
Install Doors |
5 days |
Mon 12/30/19 |
Fri 1/3/20 |
43 |
Construction Workers |
$100,000.00 |
5.5 |
Install Windows |
5 days |
Mon 1/6/20 |
Fri 1/10/20 |
44 |
Construction Workers |
$100,000.00 |
5.6 |
Install Switch Boxes and Plugs |
5 days |
Mon 1/13/20 |
Fri 1/17/20 |
45 |
Construction Workers |
$100,000.00 |
5.7 |
Install Electric Meters and Pumping Motor |
5 days |
Mon 1/20/20 |
Fri 1/24/20 |
46 |
Construction Workers |
$100,000.00 |
5.8 |
Apply Colours on Internal Walls |
5 days |
Mon 1/27/20 |
Fri 1/31/20 |
47 |
Construction Workers |
$100,000.00 |
6 |
External Finishes |
20 days |
Mon 2/3/20 |
Fri 2/28/20 |
$400,000.00 |
||
6.1 |
Apply Colours on External Walls |
5 days |
Mon 2/3/20 |
Fri 2/7/20 |
48 |
Construction Workers |
$100,000.00 |
6.2 |
Apply Designs |
5 days |
Mon 2/10/20 |
Fri 2/14/20 |
50 |
Construction Workers |
$100,000.00 |
6.3 |
Paint Names of Each Boarding House |
5 days |
Mon 2/17/20 |
Fri 2/21/20 |
51 |
Construction Workers |
$100,000.00 |
6.4 |
Build Shades on Windows |
5 days |
Mon 2/24/20 |
Fri 2/28/20 |
52 |
Construction Workers |
$100,000.00 |
7 |
External Works |
75 days |
Mon 3/2/20 |
Fri 6/12/20 |
$1,800,000.00 |
||
7.1 |
Connect Water Tank with Water Line |
10 days |
Mon 3/2/20 |
Fri 3/13/20 |
53 |
Construction Workers, Technical Workers |
$240,000.00 |
7.2 |
Connect Electrical Lines with Main Line |
10 days |
Mon 3/16/20 |
Fri 3/27/20 |
55 |
Construction Workers, Technical Workers |
$240,000.00 |
7.3 |
Build Perimeter Walls |
15 days |
Mon 3/30/20 |
Fri 4/17/20 |
56 |
Construction Workers, Technical Workers |
$360,000.00 |
7.4 |
Build Garden Space |
5 days |
Mon 4/20/20 |
Fri 4/24/20 |
57 |
Construction Workers, Technical Workers |
$120,000.00 |
7.5 |
Build a Swimming Pool |
20 days |
Mon 4/27/20 |
Fri 5/22/20 |
58 |
Construction Workers, Technical Workers |
$480,000.00 |
7.6 |
Build a Leisure Area |
5 days |
Mon 5/25/20 |
Fri 5/29/20 |
59 |
Construction Workers, Technical Workers |
$120,000.00 |
7.7 |
Finishing Touches |
10 days |
Mon 6/1/20 |
Fri 6/12/20 |
60 |
Construction Workers, Technical Workers |
$240,000.00 |
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
The human resources that have been allocated to each of the work packages of the work breakdown structure are shown in the following table.
Resource Name |
Type |
Max. Units |
Std. Rate |
Ovt. Rate |
Cost/Use |
Accrue At |
Base Calendar |
Construction Manager |
Work |
100% |
$250.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Project Supervisor |
Work |
100% |
$300.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Construction Workers |
Work |
100% |
$2,500.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Procurement Manager |
Work |
100% |
$150.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
Technical Workers |
Work |
100% |
$500.00/hr |
$0.00/hr |
$0.00 |
Prorated |
Standard |
This report contains the details of the project scope, objectives and the overall work breakdown structure that will be followed. The work breakdown structure has been developed by dividing the entire project into several phases, sub-phases and work packages. As per the development, the work packages have been linked together using predecessor relationship as appropriate in the context of the project. The links between the work packages of the work breakdown structure are essential in determining the durations of each of the work packages. From the work breakdown structure provided above, the estimated duration for the project is 535 days and the estimated budget is $8,848,000. However, these are only preliminary estimations and will be changed in the near future in order to adjust with the project feasibility and the limitations the organization which is undertaking this particular project.
Banihashemi, S., Hosseini, M.R., Golizadeh, H. and Sankaran, S., 2017. Critical success factors (CSFs) for integration of sustainability into construction project management practices in developing countries. International Journal of Project Management, 35(6), pp.1103-1119.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Nasir, N., Nawi, M.N.M. and Radzuan, K., 2016, August. Relationship between time management in construction industry and project management performance. In AIP Conference Proceedings (Vol. 1761, No. 1, p. 020079). AIP Publishing.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction project management. John Wiley & Sons.
Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming psychological safety climate in construction project management. International journal of project management, 33(1), pp.223-235.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
Zheng, X., Le, Y., Chan, A.P., Hu, Y. and Li, Y., 2016. Review of the application of social network analysis (SNA) in construction project management research. International journal of project management, 34(7), pp.1214-1225.
We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.
Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.
Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.
Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.
Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.
Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.
We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.
Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.
You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.
Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.
Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.
You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.
You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.
Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.
We create perfect papers according to the guidelines.
We seamlessly edit out errors from your papers.
We thoroughly read your final draft to identify errors.
Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!
Dedication. Quality. Commitment. Punctuality
Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.
We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.
We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.
We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.
We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.