National Archives Of Australia Website Development And Hosting Report

Work breakdown Structure

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Figure 1: Work breakdown Structure

(Source: Created by Author)

The schedule for the upgradation of website for National Archives Australia is given in the table below which reflects on the unique identifier, phases, descriptive task, milestones, duration as well as resources.

WBS

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Task Name

Milestones

Duration

Start

Finish

Dependency

Resource Names

0

Upgradation of website for National archives of Australia (planned)

118 days

Mon 19-11-18

Wed 01-05-19

1

   Project initiation phase

16 days

Mon 19-11-18

Mon 10-12-18

1.1

      Development of business case

4 days

Mon 19-11-18

Thu 22-11-18

Project manager, Project planner

1.2

      Undertaking feasibility study

3 days

Fri 23-11-18

Tue 27-11-18

2

Financial manager

1.3

      Establishment of project charter

4 days

Wed 28-11-18

Mon 03-12-18

3

Project manager, equipment [1],service

1.4

      Appointment of team members

5 days

Tue 04-12-18

Mon 10-12-18

4

Project manager

M1

Milestone 1: Completion of initiation phase

0 days

Mon 10-12-18

Mon 10-12-18

5

2

   Project planning phase

20 days

Tue 11-12-18

Mon 07-01-19

2.1

      Project plan development

5 days

Tue 11-12-18

Mon 17-12-18

5

Developer, Project manager, Supervisor, equipment [1], Project planner

2.2

      Resource plan development

4 days

Tue 18-12-18

Fri 21-12-18

6

Project manager, Project planner

2.3

      Financial plan development

5 days

Tue 18-12-18

Mon 24-12-18

8

Technical engineer

2.4

      Project quality plan development

6 days

Mon 24-12-18

Mon 31-12-18

9

Developer, statutory cost, System analyst

2.5

      Risk management plan development

4 days

Tue 25-12-18

Fri 28-12-18

10

Project manager, materials [1],Risk analyst

2.6

      Project acceptance plan

5 days

Tue 01-01-19

Mon 07-01-19

11

Project manager, Supervisor, Project planner, service

2.7

      Communication plan development

6 days

Mon 31-12-18

Mon 07-01-19

12

Risk analyst, statutory cost

M2

      Milestone 2: Completion of planning phase

0 days

Mon 07-01-19

Mon 07-01-19

13

3

   Project designing phase

15 days

Tue 08-01-19

Mon 28-01-19

3.1

      Wireframe design

5 days

Tue 08-01-19

Mon 14-01-19

14

Developer, equipment [1], materials [1], Technical engineer

3.2

      Visual design

4 days

Tue 15-01-19

Fri 18-01-19

17

Developer, Financial manager, Project planner, Technical engineer

3.3

      Design of prototype

6 days

Mon 21-01-19

Mon 28-01-19

18

Project manager, equipment [1], Project planner, System analyst

M3

Milestone 3: Completion of designing phase

0 days

Mon 28-01-19

Mon 28-01-19

19

4

   Development phase

36 days

Tue 29-01-19

Tue 19-03-19

4.1

      CMS implementation

7 days

Tue 29-01-19

Wed 06-02-19

19

materials [1], Project planner, Risk analyst

4.2

      Front end development

8 days

Thu 07-02-19

Mon 18-02-19

22

Developer, Financial manager, System analyst

4.3

      Black end development

9 days

Tue 19-02-19

Fri 01-03-19

23

Developer, equipment [1], materials [1],service

4.4

      Database development

12 days

Mon 04-03-19

Tue 19-03-19

24

Developer, Project manager

M4

Milestone 4: Completion of development phase

0 days

Tue 19-03-19

Tue 19-03-19

25

5

   Testing phase

22 days

Wed 20-03-19

Thu 18-04-19

5.1

      Testing of black box

5 days

Wed 20-03-19

Tue 26-03-19

26

Project manager, Project planner, service

5.2

      Testing of user acceptance

8 days

Wed 27-03-19

Fri 05-04-19

28

Developer, Project planner, Risk analyst, statutory cost, System analyst

5.3

      Compatibility testing

9 days

Mon 08-04-19

Thu 18-04-19

29

statutory cost, System analyst

M5

      Milestone 5: Completion of testing phase

0 days

Thu 18-04-19

Thu 18-04-19

30

6

   Closure phase

9 days

Fri 19-04-19

Wed 01-05-19

6.1

      Website hosting

3 days

Fri 19-04-19

Tue 23-04-19

30

Project manager, Fees and charges, Project planner, Technical engineer

6.2

      Review of project

2 days

Wed 24-04-19

Thu 25-04-19

33

Project manager, Project planner

6.3

      Analyzing stakeholders

2 days

Fri 26-04-19

Mon 29-04-19

34

Developer, Fees and charges, Project planner, statutory cost

6.4

      Project documentation

2 days

Tue 30-04-19

Wed 01-05-19

35

Developer, Fees and charges, System analyst, Technical engineer

M6

     Milestone 6: Completion of project closure phase

0 days

Wed 01-05-19

Wed 01-05-19

36

The critical path of the project is provided below:

Figure 2: Critical path

(Source: Created by Author)

It is found that the critical path that is reflected in red in the above figure helps in making different types of decision within the project. It is identified that critical path method helps in shortening timelines of the project as well as assists in improving resource management. In addition to this, the critical path method is utilized for comparing the planned progress with the actual progress of the project. With the help of critical analysis, the project managers can be able to determine the tasks that has been already completed with the prediction of the remaining tasks in progress. This further helps the project managers to make proper decision related with the project so that the entire project can be finished within the expected time and budget.

The schedule baseline will be communicated to the stakeholders with the help of methods that are generally elaborated below:

Project reports: Project reports are considered as the most common way of communicating the schedule baseline with the stakeholders of the project. The project report may contain proper information as well as details about the schedule baseline that generally assists in providing proper overview about the project.

Slides and presentation: Slides as well as presentation is another way of visually communicating information related with schedule baseline to the project stakeholders. This method can be utilized for communicating to large group by ensuring that each of the stakeholders can get the same information.

Online tools: Online tools can be utilized for communicating with the stakeholders of the project. It is found that the utilization of Seavus project viewer assists in providing online access of Microsoft project so that the stakeholders can be able to get proper overview about the schedule baseline of the project.

It is found that both planned as well as actual tracking schedule is provided in the form of Gantt chart which reflects the variation between actual as well as planned.

Figure 3:  Planned tracking Gantt chart

(Source: Created by Author)

Figure 4:  Actual tracking Gantt chart

(Source: Created by Author)

 The options that are available in order to bring the project back are generally listed below:

  • Focussing on managing time of the project
  • Reviewing the utilization of resources
  • Allocating more resources
  • Proper management

In order bring the project back to the schedule, a greater number of resources are allocated within the project with proper management so that the entire project can be completed as per the actual plan.

The processes that will be put in place are elaborated below:

 Measure: The time of the project schedule is measured with the help of time tracker as well as percentage of work completed in project.

Record: It is found that in order to track information related with the project, the project manager create project files as well as project documents

Project progress of activities: Periodic review of project schedule must be done in order to know the progress of the project.

 It is found that in order to implement the agreed schedule changes, it is very much necessary to undertake steps that are generally elaborated below:

Updating baseline of the project: It is quite necessary to update the baseline of the project for implementing the agreed schedule changes.

Changing the scope of the project: The scope management plan must be changed due to the addition of agreed changes within the project.

Updating the change log: The change log must be updated for successful implementation of the schedule changes within the project.

 It is identified that the project performance is on time and as per the assumed completion date of the project. This is because, time of the project is managed quite effectively and if schedule slippage is seen in any of the project activities, it is managed by doing extra work so that the next activity of the project can get completed within the assumed time as per the schedule. Moreover, the project managers engage in planning schedule management as well as undertaking earned value analysis for finishing the entire project on time.

The time management issues that are faced or experienced while undertaking the project is elaborated in the table below:

Date

 Description of problem/opportunity

Recommended action for next time/project

Lessons learnt raised by

 30-11-2018

It is found that I faced problem in developing the project charter properly due to availability of improper information about the project.

It is necessary to gather all information that are important about the project before developing the charter of the project.

 The team members must involve in data and information bout the project.

05-12-2018

Faced problem in recruiting team members due to lack of time.

Recruitment must be done by taking time as the skills of the hired team members will affect the project outcome.

It is necessary for the project managers to provide some more time for hiring process.

28-01-2019

Faced challenges in finishing the prototype design of time due to unskilled members

It is necessary to hire experienced designers.

The human resources must test the skills of the designers before hiring them.

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Braglia, M., and Frosolini, M. (2014). An integrated approach to implement project management information systems within the extended enterprise. International Journal of Project Management, 32(1), 18-29.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., and de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Joslin, R., and Müller, R. (2015). Relationships between a project management methodology and project success in different project governanQce contexts. International Journal of Project Management, 33(6), 1377-1392.

Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., and Villanueva, P. (2014). Project risk management methodology for small firms. International journal of project management, 32(2), 327-340.

Sánchez, M. A. (2015). Integrating sustainability issues into project management. Journal of Cleaner Production, 96, 319-330.

Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., and Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.

Too, E. G., and Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP