Kurie Kurie Town With Heart Mural Project For Unique Identity & Tourism Attraction

Background of Kurie Kurie Town with Heart Mural Project

The Town with Heart community program was going to be arranged in the small town named as Kurie Kurie. The project was undertaken for establishing Murals or wall painting in the town. The project of wall painting was started in the year 2004. This program creates the unique identity of the Kurie kurie town all over the world. In this paper we are going to innovate the town with the arrangement of Town with Heart Mural project so as to bring pride and prosperity to the city. The group of community involved should cooperate in different sectors such as business, education, health, council, cleanliness, tourism, youth education, and others. The good quality portrait of the murals on the walls will result in attracting huge amount of tourism within the small town. The project manager should actively participate in guiding the local people of the area about the advantages of drawing murals in their locality. In this paper, we are looking forward to improve the quality of designing the murals for the small town so as to increase the rate of tourism.  

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The project is laid down for paintings murals on walls of the town to increase its popularity and make it a unique city. The murals can designed on different themes chosen from the background of emerging communities. The local community people and artists plays an important role in the development of the mural design because it helps in reflecting the real religious and social activities of the undertaken community. The assets of the local community members help in attracting large tourism towards the small town kurie kurie. Every mural drawn on the wall should depict special quality and culture of the correspondent community. The community representation should guide the artist about what to include and what to exclude from the designing forum of the murals. The project is implemented for drawing five murals throughout the walls of the town. The mural trails have to be developed in the town. During the initialization of the project, some of the social and ethical issues exist with people of local community. The project requires overcoming and resolving the problem of conflict which exists between the employer and the local people of the town because it can affect the feeling and emotions which are associated with the religious activity of their community.

The mission of completing this project is to develop a Kurie Kurie town into a unique city with the implementation of murals and wall paintings on the walls of the town placed throughout the area undertake for the development. It helps in attracting large number of tourism towards the town which helps in improving the economic condition of the city. It provides employment to the large amount of residential people. The city is get equipped with the unique attraction sites. The prosperity of the community culture get improved. The generation of murals helps in creating historical sites for the tourists. The pride and prosperity for the local community can be improved. The assistance given by the local community members to the artists helps in drawing the clear and concise representation of the local community culture. The inclusion of the community members can be increased on the development of developing murals. The leadership plays an important role from the selection of mural to the deployment of it on the wall of the town because social and ethical issues can take place since the feelings and emotion of the local people is attached with the religious activity of their community. These issues have to be resolved with extra care to overcome the problem of disputes and chaos in the working community group. The painting of one community can affect the feelings and emotions of the other community members. Therefore, the confidence has to be built up among the community members by arranging periodic meetings between them. The leader should possess good communication and grievance handling skills for the smooth functioning of the project. The study of literature review of the past experience helps in adding new views, ideas, and thoughts to the designing agenda and elimination of the design on which negative feedback had been generated by the tourists.  The local government and corporate authorities should support the development of murals on the wall of the town. The project should aim on increasing the sponsorship for achieving the long term developing of the project which results into increasing tourism throughout the world for increasing the economic condition of the small town.

Community Cooperation for Mural Project

The objective of the project is to create ten murals throughout the walls of the town to represent the culture and the religious activities performed by different community of the locality. The development of the murals helps in increasing the point of attraction of the tourists. The project manager should set the criteria for the development of the murals. The regular meetings should be arranged with the community members for assisting the artist and building confidence to overcome the problem of disputes and chaos. The budget of the program should be approved for taking sponsorship to achieve long term of the project. The project manager should develop teams for the selection of the site area and location. The analysis of the project sponsor is the key responsibility of the project manager for the long term sustainability of the undertaken project. The owners of the walls should be contacted for granting permission to develop the mural on their walls for increasing the prosperity and pride for their community and town. The documentation of legal, social, political, and ethical issues should be properly carried out so as to minimize the chance of any distraction during the implementation of the planned program. The rendering of the walls involves the approval of the mural content which should be painted on the walls of the city. After the approval of the mural content, the artists should assists for drawing the paintings by the local community members. Mock up murals should be prepared for taking final approval from the local members to start painting on the walls of the town (Obrutsky, 2016). The approval of the sponsorship is the important step for managing the financial resources for the undertaken project.

The following diagram shows the project life cycle diagram of the undertaken project of constructing murals on the walls of the Kurie Kurie town to make it unique in the near surrounding so that the point of attraction can be improved for increasing the flow of tourist in the city (Passenheim, 2013). It helps in improving the economic condition of the city and the local community members. 

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Each phase of the project life cycle is described in the table below:

Project Phase

Project Activities

Description

Concept Phase

Contact the department of art, culture, and tourism

Form team, and establish team leaders

Identify and select sites

Determine criteria for murals

Research and develop mural content

The project manager should take the privilege to contact with the artist and tourism for the deployment of the wall painting. The teams should be selected for determining the information which is to be described in the mural laid down (Wagnar, 2017).

Feasibility

Conduct Site inspection

Research and identity artists, organizations, galleries for inspection

Determine and document legal responsibilities

Apply for grant funding

Seek Sponsorship

Obtain quotes for rendering and scaffolding artist material

The project  manager should undergo feasibility analysis of the project requirement for the deployment of the wall painting on the walls of the town. The project manager should select best quality of artists (Zlatanova, 2012). He should analyse the social, political, legal, and ethical issues which are incorporated with the local community members. The analysis of the project sponsor is the key responsibility of the project manager for the long term sustainability of the undertaken project (Ayidinli, 2017). The cost of material required for the completion of the project should be estimated.

Outline Design

Meeting with community groups to confirm their commitments

Murals content to be approved

The confirmation on the information and values added in the design of the murals should be taken so that the omission of disputes and distraction can be done. The approval of the murals from the local community should be clearly done.

Planning

Community assistants to the artists to be selected

Artists to be selected and brief

Murals content to be approved

Project manager should undergo brief planning activities by taking assistance from the local community members and the executives of the project team.

Detailed Design

Mock-up of murals to be prepared

Arrange grants and sponsorship meeting

Draft project implementation plan

Mock-up of the murals help in studying of the exclusion of inclusion of the design in the development of the wall painting so that the feeling and emotion of the local residential people should not be hurt with respect to their religion and culture. Arrangement of periodic meetings with the project sponsors helps in developing good and healthy relationship between them which in turn result in the constant flow of cash for the proper functioning of the project.

Procurement

Develop invite for networking function and  distributes to galleries and artists

Assemble scaffoldings

Distribution of the design helps in developing good network with the common people. Scaffoldings of the design should be assembled periodically.

Construction

Contacts wall owners

Render walls

Paint murals

Launch murals to media, community

The approval should be taken from the wall owners for developing the design of the mural on their correspondent site. The designing of the murals on the walls of the town help in providing unique feature to the city (Saini, 2012)

Cost Control

Development of the budget report

The budget should be prepared so as to analyse the difference in the actual and the budget cost which helps in minimizing the extra expenditure in carrying over the designing part of the murals (Barjtya, 2017)

Quality Control

Development of the quality control report

The report of quality control helps in measuring the difference in the expectation of the wall owner and the actual design produced by the artists. The satisfaction level of the local community members helps in specifying quality of the mural drawn on the wall.  

Maintenance

Approval for long term of the project

The satisfaction level and the pride and prosperity to the town result into the long term sustainability of the project (Perkins, 2012).

Name of the stakeholder

Expertise of the stakeholder

Position

Responsibilities

G. Brown

Leadership

Planning

Project Manager

The project manager is responsible for the selection of the site, team members, planning activities, providing roles and responsibility to the team members, meeting with sponsors, artists, contractors, and wall owner (Roll, 2011).

W. Swaminathan

Managing project Team

Coordination among activities

Team Leader

Dividing work among the team participants

Scheduling of activities (Liviu, 2014)

Getting reports from the subordinate and submitting to the project manager

K. Davis

Designing

Chief Designer

Transforming information collected from the local assistant into the mural designing

L.M. Prasad

Drawing and painting

Chief Artist

Portrait the design of the mural on the wall of the town with the assistance of his sub-ordinate and team members

W. Wang

Good communication skills

Local Community Assistant

Assist the chief designer in communicating the cultural and religious activity of the local people for developing the murals (Daldanise, 2010)

D. Thomson

Managing supply and demand of the resources on the site

Contractor

Managing supply and demand of the resources on the site

R. Radhakrishnan

Communication skills

Sub-contractor

Approval of the mural

F. Linga

Preparing budget

Financial Manager

Maintaining budget, cash inflow and outflow, cost analysis matrix, and others

D. Dewis

Predicting quality

Quality manager

Developing the quality report for pointing out the gaps which exist with the requirement specification plan and portrait drawn on the wall by the artists.

Stakeholder

(Who)

Information

(What)

Purpose

Frequency

Methodology

Project Manager

Roles and responsibility of the team members and the content required in the murals for the development of the wall painting

To make the town unique and help in increasing the prosperity all over the world

High

During the project initialization phase

Team Leader

Collects the report from the subsequent team members

To take the design of the portrait according to the requirement specification plan

Weekly

Throughout the project

Chief Designer

Assitance from the local community member for depicting the cultural heritage of the local resident into the murals

Feeling and emotion of the local people should not be hurt

Monthly

Throughout the designing of the murals

Chief Artist

Take assistance from the local executives and designer

It help in making the cultural heritage design on the walls of the town

Daily

During the paintings of the murals

Local Community Assistant

Give the clear understanding of cultural and religious activities of the local people

Feeling and emotion of the local people should not be hurt

Daily

During the painting of the murals

Contractor

Managing supply and demand of the resources on the site location

For the smooth functioning of the project activities so that painting of murals can be completed within the approved budget and time allocated

Daily

During the complete project life cycle

Project on Town with Heart community program

Phase

Activity

Responsible stakeholder

Start date

Finished Date

Project Initiation

Contact the department of art, culture, and tourism

Project Manager

22-Mar-2018

28-Mar-2018

Form team, and establish team leaders

Project Manager

28-Mar-2018

01-Apr-2018

Identify and select sites

Teams

02-Apr-2018

11-Apr-2018

Requirement analysis

Determine criteria for murals

Team leaders and project manager

12-Apr-2018

16-Apr-2018

Conduct Site inspection

Project manager

17-Apr-2018

01-May-2018

Research and identity artists, organizations, galleries for inspection

Project team

01-May-2018

07-May-2018

Determine and document legal responsibilities

Project manager

07-May-2018

13-May-2018

Apply for grant funding

Project manager

14-May-2018

20-May-2018

Seek Sponsorship

Teams

21-May-2018

30-May-2018

Obtain quotes for rendering and scaffolding artist material

Project manager

30-may-2018

13-Jun-2018

Research and develop mural content

Teams

13-Jun-2018

27-Jun-2018

Meeting with community groups to confirm their commitments

Project manager

28-Jun-2018

02-Jul-2018

Designing and development

Murals content to be approved

Subcommittee of team

29-Jun-2018

05-Jul-2018

Artists to be selected and brief

Teams

05-Jul-2018

11-Jul-2018

Community assistants to the artists to be selected

Teams

11-Jul-2018

13-Jul-2018

Mock-up of murals to be prepared

Artists

13-Jul-2018

14-Jul-2018

Arrange grants and sponsorship meeting

Project manager

14-Jul-2018

15-Jul-2018

Draft project implementation plan

Project Manager

11-Jul-2018

15-Jul-2018

Develop invite for networking function and  distributes to galleries and artists

Project team

11-Jul-2018

17-Jul-2018

Implementation

Assemble scaffoldings

Contractor

01-Jul-2018

05-Jul-2018

Contacts wall owners

Project manager

04-Jul-2018

10-Jul-2018

Render walls

Contractor

10-Jul-2018

12-Jul-2018

Paint murals

Artist, community assistants

12-jul-2018

13-Jul-2018

Launch murals to media, community

Team leaders, project manager

10-Jul-2018

14-Jul-2018

Seeks Sponsorship

Team

13-Jul-2018

19-jul-2018

Project closure

Write a close out report

Project manager

13-Jul-2018

19-jul-2018

Agile Project methodology is the best suitable methodology for the undertaken project work of portrait the cultural heritage of the local residential people on the walls of the town which helps in attracting new tourist towards the city and in turn helps in increasing the financial condition of the common people. The purpose of implementing the agile methodology is to resolve the social and ethical issues which exist with the local community so that the deployment program can be achieved flawless in the designing of the religious and cultural activities of the residing people.

The manifesto of the agile methodology is based 12 working principles which are categorised as setting of the priority in flow of activities for raising the satisfaction level of the local community members, the change in the requirement of the participants can be taken under consideration during any phase of the project life cycle model as discussed in the table above, the mock up design of the murals can be delivered within the couple of weeks for satisfying the participants with the delivery of the final product, regular meetings should be arranged between the artists and the chief executive head of the local community members, motivating the artists for achieving the design specification according to the requirement placed by the local people, increasing efficiency and effectiveness of transmitting information through the murals developed showing the cultural heritage of the local people, the success of the design can be measured with the mock-up design of the murals developed, the deployment of the agile methodology works on achieving the long term sustainability program, undertaking the technical risks under consideration so as to achieve success of the project, maximizing the working amount and throughput of the labour, and reflection of the team and effectiveness of the project at meeting arranged in regular interval of time. The following diagram shows the working structure of the agile methodology for the construction of the murals: 

The implementation of the agile methodology is justified  for the given case study because it helps in mock up delivery of the murals for improvement at the early stage so that the cultural heritage of the local people should not be hurt. The improvement in the final design can be done according to the changing requirement of the local people. They have the authority to include and exclude the area of concern according to their own choice. The artist will work after the approval of the mock up design from the local resident people. The mock up design delivery help in raising the satisfaction level of the participating bodies which helps in motivating the Excellency in the working labour class. The integration and the coordination among the stakeholder helps in ensuring the success of the project which results into the long term sustainability action plan. The integrated meetings should be arranged among the participating bodies so as to explore sharing of large amount of information. The gaps should be studied for removing the design which can hurt the feeling and emotions of the local people. During the initialization of the project, some of the social and ethical issues exist with people of local community. From the past experience, it can be studied that the designing of the murals on the walls of the town is the successful project because the tourism activity in increased from the last decades. The literature review of the past experience helps in adding new views, ideas, and thoughts to the designing agenda and elimination of the design on which negative feedback had been generated by the tourists. The flow of communication should be effectively managed between different stakeholders so as to carry the work in progress smoothly. The working system helps in designing the murals on time so that the economic condition of the area can be improved.

Risk Categorisation

Risk Identification

Risk Management

Technical risks

Unclear requirement specification plan

Local community members are unwilling to share their cultural activities

Local community members are unable to assist the artists

Non availability of expert artists

Non availability of expert labours

Non availability of equipment

Requirement specification plan should be clearly discussed with the local community members and the undertaken project team so as to resolve the flaws and obscure through the communication process.

Periodic arrangement of meetings with the local people

Two or more local assistants should be appointed

Equipment should be available before demand

Working criteria of management

Wrong selection of the team members

Mismanagement of supply and demand of the raw material on the site

Unclear plan for the deployment of mural activities

Problem associated with the leadership quality of the manager

Problems in the implementation plan

Team should be selected on the basis of expertise and talent.

Supply and demand of the resources should be met on time

Periodic arrangement of meetings with the local people

Social Risks

No support of local community

Feelings and emotions of the local people get hurt

Unwilling to share their cultural practices

Requirement specification plan should be clearly discussed with the local community members and the undertaken project team so as to resolve the flaws and obscure through the communication process.

Periodic arrangement of meetings with the local people

Two or more local assistants should be appointed

Legal risks

Government put restriction on the deployment of the project

Delay in the approval of the project

Government assistance should be taken before the initialization of the project so that the feelings of the local community members should not be hurt.

Financial Risks

Limited amount of sponsorship

Difference in the price of raw material

Limited amount financial support in managing supply and demand of the raw material on the construction site

Proper communication should be made with the project sponsor

The requirement of the murals and profit gained by the murals should be clearly defined to the project sponsor

Interest rate should be increased by communicating the advantages of developing the mural design on the walls of the city

From the literature review of the town, we have concluded that the risks increased during the festival time because the flow of immigrants in the city increased. The risks management plan has to be designed to resolve the problem associated with the canoe rides. The canoe rides is the exclusive program of the town to show the tourist their cultural heritage drawn on the walls of the town through the placement of canoe in the river. The tourist enjoy the canoe rides with the assessment of cultural and religious heritage of the people. The following table shows the brief description of the risks associated with the canoe rides during the festival activities:

Risk

Probability of occurrence

Impact

Priority

Canoe training exercise on the rivers and river side flats

During the festival activities

The routine activities of the local resident people who live near the shore of the river can be affected due to the increase in traffic on the river side (Filippov, 2008). The activities like fishing get affected which can affect their eating habits

Medium

Fall off or other mis-happen during the canoe rides

Monthly

The flow of river can result into mishappening in the canoe rides. The tourists and the canoe driver should use the safeguards during the riding program

High

Mismanagement in the parking of the canoe at the river shore

Daily

The entering and exit of the canoe is not properly managed on the river bank which results into the increase of traffic on the shore. This result in creating the bag image of the town in the tourist mind which in turn can result into decreasing level of tourism

High

Feedback

Daily

Feedback should be collected from the tourist which helps in improving the facility providing to the tourist. The positive feedback helps in motivating to bring accuracy in the development of designing the murals and negative feedback increases the labour work to provide the good quality work to the tourists which helps in making the Kurie Kurie town a unique one.

High

The project manager should schedule the inspection program with the corresponded team members on the site for checking the work done by the team (Jetter, 2015). The gaps in the planned and the actual output in the quality of the murals should be resolved on the site of flaws so that the quality can be improved. The project manager should take the privilege to contact with the artist and tourism for the deployment of the wall painting. The project manager is responsible for the selection of the site, team members, planning activities, providing roles and responsibility to the team members, meeting with sponsors, artists, contractors, and wall owner

 The quality of the murals drawn on the walls of the town is the important factor for increasing the tourism in the city. It helps in depicting the historical culture of the local resident of the people. The quality control processes should be implemented for checking the quality of painting periodically. The dialy reviewing reports should be submitted by the team executives to the project manager. The increasing rate of tourism depends upon the quality of murals produced by the artist in depicting the historical culture of the community members because the pride and prosperity helps in attracting new tourists towards the area. The regular meetings should be arranged with the community members for assisting the artist and building confidence to overcome the problem of disputes and chaos (Catalini, 2015).  The accuracy in the wall paintings can be drawn by taking assistance from the local community members in the development of quality register. The proactive policies help in defining the painting up to the requirement specification plan. The procurement of the raw material and the resources should be managed by taking continual assistance with the contractor. The approval of the project plan should be done for the implementation of murals on the wall the town. The social issues exist with the local community members should be resolved at first hand to overcome the problem of disputes and distraction later in the implementation period of the project. The periodic inspection should be done of the painted murals by the head of the local community members and the project manager for assisting the correction required before the final delivery of the project. The project manager should arrange the meeting for briefing out the roles and responsibilities to the team members for completing the project of drawing murals within the period of three months. The performance of the contractor should be researched before signing the project so that the quality of the output received should be maintained. The risks involved with the deployment of the project can be minimised by forecasting and proactive planning of risk identification and management program. The social and the legal issues should be resolved before the implementation of the project (Ozorhon, 2011). The inclusion of the assistance from the local community members helps in improving the level of confidence that their cultural heritage will not be harmed. The propaganda of the cultural activities through the designing and painting of the murals help in increasing the profit of the common resident of the area (Bossink, 2013).

Project Life Cycle of Mural Project

The deployment of tactics of quality management plan is to improve the level of quality of the murals developed during the mock up designing phase in the deployment of agile methodology (Perez, 2012). The analysis of the gaps between the required design and the mock up design created by the designer helps in resolving the flaws in the final design (Abott, 2012). Project manager, artist, and the local resident head are involved in the deployment of the quality plan because the local head is applicable for predicting the defects in the mock up design of the murals created by the artists. The project manager passes the order for changing the required defects

Defects

Priority

Improvement plans

Cultural heritage of the community is not synchronised

High

The synchronization of the historical event is the most important tasks because it helps the tourist to get through the improvement in the culture of the local people

Clear understanding of the design

High

The artist should be very peculiar in constructing the design of cultural heritage on the walls of the town

Mismanagement at the shore area of the river

High

It can result into casuality

Budget:

Name of the project: Town with Heart community program

Source of Income

Approved budget

Actual budget

Difference

Funds approved by project sponsors

$20000

$20000

0%

Income received

Total expenses of the project

Budgeted cost

Actual cost of the project

Difference

Strategies required in collecting the information required for the mural information

$ 1900

$ 2300

25%

Policies in relationship with marketing strategies

$ 2400

$ 3000

6.34%

Team members

$2600

$ 2200

15%

Arrangement of artists

$ 5500

$ 4900

6%

Availability of raw material

$ 1400

$ 2500

53%

Subtotal

$ 13400

14,300

8.24%

Total

14,400

From the study of literature review and past experience of the given project, it is recommended that the designer and artists should take proper participation of the local community member so that they can guide accurately their requirement. The project manager and the team leaders should possess good communication skills so that the local people should feel comfortable in sharing their views and ideas to make their town unique in that area. The uniqueness of the town helps in increasing the rate of tourism (Lano, 2017). The economic condition of the local people can be improved by sustaining the construction of murals on the walls of the town for long term because It is the pride moment for the people as their cultural heritage and religious activity are so powerful that they are capable of attracting large amount of tourism. They should take step forward in exploring the work done by their ancestor in reserving their cultural forum. The good quality portrait of the murals on the walls will result in attracting huge amount of tourism within the small town. The project manager should actively participate in guiding the local people of the area about the advantages of drawing murals in their locality. The approval of the project plan should be done for the implementation of murals on the wall the town. The social issues exist with the local community members should be resolved at first hand to overcome the problem of disputes and distraction later in the implementation period of the project.  The local people should be aware of the power of uniqueness of the town. The quality management plan should be taken under consideration so as to deploy and deliver good construction agile methodology in developing the wall paintings.

Conclusion

It is concluded that the agile project methodology helps in eliminating the flaws in the mock up design of the murals at the early stage by taking association and guidance from the project manager and the local head of the community. The final design of the mural is capable of raising the satisfaction level of the local community in delivering their cultural heritage at the global level for attracting millions of tourists towards their small town. The implementation of the agile methodology helps in resolving the social and ethical issues which exist with the local community so that the deployment program can be achieved flawless in the designing of the religious and cultural activities of the residing people. The approval of the project plan should be done for the implementation of murals on the wall the town. From the past experience, it can be studied that the designing of the murals on the walls of the town is the successful project because the tourism activity in increased from the last decades. The documentation of legal, social, political, and ethical issues should be properly carried out so as to minimize the chance of any distraction during the implementation of the planned program.

References: 

Abott, C. (2012). Best practices in project delivery system. Retrieved from https://www.irbnet.de/daten/iconda/CIB16211.pdf

Ayidinli, D. (2017). Software project management anti patterns in innovation project. Retrieved from https://tampub.uta.fi/bitstream/handle/10024/97770/GRADU-1436947648.pdf;sequence=1

Barjtya, S. (2017). A detailed study of software development life cycle model. Retrieved from https://ijecs.in/issue/v6-i7/32%20ijecs.pdf

Bossink, B. (2013). Managing drivers of innovation in construction networks. Retrieved from https://research.vu.nl/ws/portalfiles/portal/2041422

Catalini, C. (2015). Slack time and innovation. Retrieved from https://www.hbs.edu/faculty/Publication%20Files/16-106_782e5e6b-ef9c-4149-a48a-9778636a53bc.pdf

Daldanise, G. (2010). Innovative strategies of urban heritage management for sustainable local development. Retrieved from https://ac.els-cdn.com/S1877042816303986/1-s2.0-S1877042816303986-main.pdf?_tid=ccbf05aa-b30d-494f-986d-3baec98dad7c&acdnat=1521709613_98721455996edd1ad060d861651f00ff

Filippov, S. (2008). Innovation project management: A research agenda. Retrieved from https://pucsp.br/icim/ingles/downloads/papers/TL_038.pdf

Jetter, A. (2015). The practice of project management in product development. Retrieved from https://www.pmi.org/-/media/pmi/documents/public/pdf/research/practice-project-management-product-development.pdf

Lano, K. (2017). Literature survey of previous work in models and methodologies in project management. Retrieved from https://thesai.org/Downloads/Volume5No9/Paper_17-Literature_Survey_of_previous_research_work_in_Models_and_Methodologies_in_Project_Management.pdf

Liviu, M. (2014). A Comparative study on software development methodologies. Retrieved from https://dbjournal.ro/archive/17/17_4.pdf

Mishra, A. (2013). A comparative study of different software development life cycle models. Retrieved from https://www.ijarcsms.com/docs/paper/volume1/issue5/V1I5-0008.pdf

Obrutsky, S. (2016). Comparison and contrast of project management methodologies. Retrieved from https://www.researchgate.net/publication/305969672_Comparison_and_contrast_of_project_management_methodologies_PMBOK_and_SCRUM

Ozorhon, B. (2011). Innovation in construction: A project lifecycle approach. Retrieved from https://www.irbnet.de/daten/iconda/CIB16211.pdf

Passenheim, O. (2013). Project Management. Retrieved from https://home.hit.no/~hansha/documents/theses/projectmanagement.pdf

Perez, N. (2012). Research methodology: An example in the real project. Retrieved from https://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.541.9222&rep=rep1&type=pdf

Perkins, R. (2012). A study of the design process. Retrieved from https://www.designcouncil.org.uk/sites/default/files/asset/document/ElevenLessons_Design_Council%20(2).pdf

Roll, G. (2011). United smart cities. Retrieved from https://www.unece.org/fileadmin/DAM/hlm/projects/SMART_CITIES/United_Smart_Cities_Project_Document.pdf

Saini, M. (2012). A review of open source software development model. Retrieved from https://pdfs.semanticscholar.org/198e/62d2d305bc23b0e8101a36a13cf875e001e1.pdf

Wagnar, J. (2017). Innovation spaces: The new design of work. Retrieved from https://www.brookings.edu/wp-content/uploads/2017/04/cs_20170404_innovation_spaces_pdf.pdf

Zlatanova, R. (2012). Smart cities: Project Guide. Retrieved from https://www.smartcities.info/files/Smart%20Cities%20Project%20Guide_1.pdf

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP