Fundamentals Of Project Management: Deliverables And Challenges

Project definition/Parameters and risks

The purpose of this report is to demonstrate the ability of the decision making regarding the overall delivery and management of an entire project. DBCL Engineering, a marine and offshore construction company operates in the large fabrication yard on the North East Cost of England. Pretoria Oil project is won by the DBLC Company that is expected to be delivered before 21st September 2018. Project managing includes an extended knowledge on the best practices and decision-making that can enhance the productivity of the project and manages to deliver the project within the estimated constraints. Considering the deployment of this project, project planning and management needs to delivered in an efficient and effective way as the company can have high penalties of the project is not delivered within time and proposed budget. This is highly deemed project for the DBCL Company and hence, the planning is being proposed in this project.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The project manager needs to consider the project scope, time, cost and quality as the most critical factors for the successful and efficient delivery of the project. ‘Iron triangle’ is being represented as the “metaphor pointing out that the project manager is asked to reach a reasonable trade-off among various concurrent, heterogeneous, and visible constraints (Muller 2017).” The traditional iron triangle can be demonstrated as schedule, budget, scope and quality of the project.

Schedule: There is schedule constraint which affects start as well as end date of the project. It is seen that the project work was started on time but due to delay occurred because of Pretoria is entitled to demand. The completion date is 21st September, 2018 and delay in the project causes DBCL to pay Pretoria Oil a damage of £500,000.  

Scope: DBCL is not able to meet with project goals, deliverables and project tasks; therefore it provides a huge effect on the project boundaries. 

Budget: DBCL faces budget constraint as its estimated budget was £59.5m, and it is exceeded its budget limit to bear first 5% of the cost. The budget constraint occurs when the customers are limited in the consumption patterns by a particular amount of income.   

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Quality: The quality of the products for the construction work should meet with the client’s requirements. DBCL has time restrictions, therefore they are required to increase resources assigned to the construction work result in quality reduction (Kerzner and Kerzner 2017). For DBLC, the construction being delivered should be capable of holding expected weights and strong in long run.

Risk Management Register for DBCL Project

Risk Identification

Assessment

Response

Monitoring and Control

Reference

Type of risk

Cause

Effect

Probability

Impact

P x L

Strategy

Trigger

Action

Responsible person/s

Review Frequency

Status date and general notes

1. 

Overextension

Increase in client demands drives the contractors and sub-contractors to take more time to handle the fabrication work.  

Project delayed

4

5

20

Mitigate

It acts as safety risk as overextension can cause defects along with site accidents.

The contractors should keep the client update of the project completion work, so that before changing demand they should analyze the risk (Basu 2017).

Project Manager, Safety Manager

Monthly

23.11.17  Register updated. Alternative safety requirements

2. 

Budget and cost escalation

improper project planning, late deivery of the milestones

project constraints not accomplished

3

4

12

Mitigate

Project manager not able to control the deliveries of the project activities

manipulating the project activities after an effective and efficient communication with the stakeholders

Project Manager

Monthly

10.12.17

Discussed with the stakeholders and work distribution is managed

3. 

Lack of Human resources or materials

Not any legal contract with the suppliers and human resources

project cost and schedule escalation

3

5

15

Mitigate

Resource manager fails to identify the importance of legal agreements

Make sure there is a legal contract and agreement between the human resources and the organization

Resource manager, Supplier, contractor

Monthly

12.12.17

Concern discussed and legal agreement issued among the different stakeholders

4. 

Accidents or natural calamity

construction constraints might not meet the expectation of the project delivery

Project delayed

1

5

5

transfer

Certain equipment fails or falls from height

Countermeasure strategy development

Safety manager, risk manager, insurance company

as required

17.12.18

Agreement between the insurance company and DBCL is made regarding the insurance of the project

5. 

Accidents due to failure of safety equipment

improper estimation of the required strength and pressure resisting property of the equipment

safety of human resources and project schedule

2

4

8

Mitigate

The safety manager did not considered the load and importance of the project delivery

Selection and utilization of best equipment considering the project safety requirements (Muller 2017)

Safety Manager, resource manager

monthly

19.12.18

Meeting with the stakeholders define the safety requirement of the project and those products purchased

6. 

Construction design fails to meet the project design

improper project designing by the project manager or utilization of less efficient tool for designing the project

project failure, schedule and budget escalation

1

5

5

Mitigate

the project designer or civil engineer did not delivered the project design in an efficient and effective manner

Using 4D drawings for the delivery of the project designing phase

Civil engineer, designer, project manager

Weekly

25.12.17

Monitoring and controlling plan is developed

7. 

Logistics and resource transferring is not being delivered to the project sites on time

transportation nnot allowing heavy vehicles to transfer

lack in resourrce availability and thus, influencing the project quality in negative manner

3

3

9

Transfer

the transportation in between the source and destination not allowing the passage for the heavy vehicles (Verzuh 2015)

contract with the contractor to deliver the resources over the sites

Contractor, resource manager

Monthly

contract or agreement with the contractor is made

8. 

Site protection

Unattended site can cause damage from leaking of pipe and theft of equipments

restriction of the project delivery

4

5

20

Monitor

Unattended site is vulnerable to project damage plus vandalism.

Draining of pipe is a method to protect the pipe from leakage.

Contractor

Weekly

21.12.17

Contractor should keep detailed records of the site and safety of equipments

9. 

Faults detected within the module of 10 weeks

Uncertainties or accidents could possibly lead to certain problems those could possibly impact on the delivered installation and thus, it would cost DBCL

The DBCL’s retained 10% money might be compromised

3

5

15

Fault detected after installation

Quality assurance program can be developed or further maintenance for the 10 weeks can be managed by the DBCL itself.

Project manager, engineers,

Quality manager

Weekly

23.12.17

Quality Assurance program adopted

10. 

Miscommunication between the DBCL engineer and engineers working for Pretoria Oil

Two group of engineers from different organizations could be a matter of agreement on same engineering concepts

The project can have many modifications that can result in cost and schedule escalation

2

5

10

During site review

Proper communication and project documentation with clarification

DBCL engineers, Pretoria Oil, project manager

Weekly

29.12.17

Communication management plan is developed with regular project documentation weekly.

The average (fully inclusive) cost of an engineer was estimated to be £59.00 per hour and for a technician £36.00 per hour. The company generally works a standard five-day week and eight-hour days. The fixed costs for each task are shown in Table 1 are in £m.

Microsoft project data feed:

The following table consist of the activities involved in this project in addition to the time required for completing the respective activity (in weeks). The resources required for the management and delivery of every activity has also been proposed. 100% resource equals one unit and hence, the percentage is allocated accordingly considering the number of resources required for delivering the proposed activity. The engineers and technicians will be paid 59 and 36 pounds per hour and hence, the cost for the activity is duration*8 times the cost per hour.

Task Name

Duration

Predecessors

Resource Names

Cost

Fixed Cost

Fabricate upper deck

4 wks

Engineers[1,000%], technicians[4,500%]

£8,400,160.00

£8,300,000.00

Fabricate cellar deck

2 wks

Engineers[1,200%], technicians[5,600%]

£7,317,920.00

£7,100,000.00

Turbine generators

6 wks

2

Engineers[800%], technicians[2,000%]

£2,786,080.00

£2,500,000.00

Fuel gas systems

2 wks

3

Engineers[600%], technicians[2,200%]

£2,891,680.00

£2,800,000.00

Fabricate flare boom

4 wks

3

Engineers[800%], technicians[3,200%]

£4,159,840.00

£3,900,000.00

Cooling systems

8 wks

4

Engineers[1,200%],technicians[1,800%]

£4,933,920.00

£4,500,000.00

Seawater pumping systems

12 wks

4

Engineers[1,200%],technicians[2,000%]

£3,185,440.00

£2,500,000.00

Connect both decks

2 wks

4,5

Engineers[1,000%],technicians[4,600%]

£3,279,680.00

£3,100,000.00

Install flare boom

6 wks

6,9

Engineers[800%],technicians[3,500%]

£2,615,680.00

£2,200,000.00

Coalescer systems

4 wks

7

Engineers[700%],technicians[1,400%]

£2,346,720.00

£2,200,000.00

Gas dehydration systems

4 wks

11

Engineers[700%],technicians[1,000%]

£2,823,680.00

£2,700,000.00

Water injection systems

6 wks

8,9

Engineers[600%],technicians[1,200%]

£3,288,640.00

£3,100,000.00

Gas compression systems

6 wks

10

Engineers[600%],technicians[1,400%]

£3,405,920.00

£3,200,000.00

Onshore commissioning

8 wks

12,13,14

Engineers[1,200%],technicians[2,400%]

£1,603,040.00

£1,100,000.00

Iron Triangle Parameters’ Importance for DBCL Project Manager

Table 1: Project Plan as per DBLC Manager

The following network diagram is prepared considering the above predecessor along with the calculation of the early start, early finish, late start, late finish, and slack in the disturbance of the project deliverables (Nicholas and Steyn 2017).

Figure 1: Network Diagram using above table

The above diagram is analysed for identifying the shortest path that can be taken by the stakeholders to meet the final delivery of the project. The A-C-G-L-N is the selected critical path as rest of the paths are taking longer time as compared to this path. It will take 36 weeks.

Figure 2: Critical path with slack calculation

The following table presents the list of the activities, required time in weeks with 8 hours of daily work and five days’ work in a week in addition to the predecessors of every activity and the initiation and finishing date.

Task Name

Duration

Start

Finish

Predecessors

DBCL Project

180 days

Mon 08-01-18

Fri 14-09-18

   Fabricate upper deck

4 wks

Mon 08-01-18

Fri 02-02-18

   Fabricate cellar deck

2 wks

Mon 08-01-18

Fri 19-01-18

   Turbine generators

6 wks

Mon 05-02-18

Fri 16-03-18

2

   Fuel gas systems

2 wks

Mon 22-01-18

Fri 02-02-18

3

   Fabricate flare boom

4 wks

Mon 22-01-18

Fri 16-02-18

3

   Cooling systems

8 wks

Mon 19-03-18

Fri 11-05-18

4

   Seawater pumping systems

12 wks

Mon 19-03-18

Fri 08-06-18

4

   Connect both decks

2 wks

Mon 19-03-18

Fri 30-03-18

4,5

   Install flare boom

6 wks

Mon 02-04-18

Fri 11-05-18

6,9

   Coalescer systems

4 wks

Mon 14-05-18

Fri 08-06-18

7

   Gas dehydration systems

4 wks

Mon 11-06-18

Fri 06-07-18

11

   Water injection systems

6 wks

Mon 11-06-18

Fri 20-07-18

8,9

   Gas compression systems

6 wks

Mon 14-05-18

Fri 22-06-18

10

   Onshore commissioning

8 wks

Mon 23-07-18

Fri 14-09-18

12,13,14

Table 2: Project Calibration

Figure 3: Gantt chart

Considering critical path, the project will be completed in 180 days and will be finished on 14th September 2018.

Total cost spent on the project: 53,038,400.00

The project will be completed before 21st September and hence, DBCL will have not to pay £500, 00 for a single time.

The revenue of the project is £59.5 m

Projected gross profit: £59.5m-£53.1m = £6.4m

On 30th April, the project report presented include the following details:

Task

Actual progress to date (%)

Total expenditure incurred to date (£m)

A

100

8.15

B

100

7.2

C

100

2.56

D

100

3.18

E

100

4.43

F

75

4.29

G

35

1.67

H

90

4.03

I

20

0.78

No other tasks had started yet or incurred any expenditure.

Table 3: actual progress and spending after 16 weeks

The following table shows the different project values after selecting the project tracking and rescheduling the project activities. The planned value of the project activities has been set as the baseline of the project based on which the progress report is calculated using MS project and following results were collected regarding the project cost, fixed cost, baseline, variance and actual budget spent till the date.

Task Name

% Work Complete

Fixed Cost

Total Cost

Baseline

Variance

Actual

Fabricate upper deck

100%

£8,049,840.00

£8,150,000.00

£8,400,160.00

-£250,160.00

£8,150,000.00

Fabricate cellar deck

100%

£6,982,080.00

£7,200,000.00

£7,317,920.00

-£117,920.00

£7,200,000.00

Turbine generators

100%

£2,273,920.00

£2,560,000.00

£2,786,080.00

-£226,080.00

£2,560,000.00

Fuel gas systems

100%

£3,088,320.00

£3,180,000.00

£2,891,680.00

£288,320.00

£3,180,000.00

Fabricate flare boom

100%

£4,170,160.00

£4,430,000.00

£4,159,840.00

£270,160.00

£4,430,000.00

Cooling systems

75%

£3,856,080.00

£4,290,000.00

£4,933,920.00

-£643,920.00

£3,217,500.00

Seawater pumping systems

35%

£984,560.00

£1,670,000.00

£3,185,440.00

-£1,515,440.00

£584,500.00

Connect both decks

90%

£3,850,320.00

£4,030,000.00

£3,279,680.00

£750,320.00

£3,627,000.00

Install flare boom

20%

£364,320.00

£780,000.00

£2,615,680.00

-£1,835,680.00

£156,000.00

Coalescer systems

0%

-£146,720.00

£0.00

£2,346,720.00

-£2,346,720.00

£0.00

Gas dehydration systems

0%

£2,700,000.00

£2,823,680.00

£2,823,680.00

£0.00

£0.00

Water injection systems

0%

£3,100,000.00

£3,288,640.00

£3,288,640.00

£0.00

£0.00

Gas compression systems

0%

£3,200,000.00

£3,405,920.00

£3,405,920.00

£0.00

£0.00

Onshore commissioning

0%

£1,100,000.00

£1,603,040.00

£1,603,040.00

£0.00

£0.00

Table 4: Actual v/s Planned values

Figure 4: Gantt chart recorded with reporting date of 30th April 2018

Tracking the project, the identified results less than the reviewed report proposed in the requirement. The reflected work completion is less than the proposed completions and hence, the project is ahead of the schedule. It was identified that the project is running ahead of the schedule and under the budget through analysing the provided result as the projected data till 30th April 2018 had low work completion percentage (Meredith et al. 2014).

After rescheduling the percentage of work completed considering the delivery and management of the every activity. The earned value table consist of following details based on which it can be said that despite of the three activities highlighted in the table, every activity of the project is under budget and going on planned schedule.

Task Name

% Work Complete

Planned Value – PV (BCWS)

Earned Value – EV (BCWP)

AC (ACWP)

SV

CV

EAC

BAC

VAC

Fabricate upper deck

100%

£8,400,160.00

£8,400,160.00

£8,150,000.00

£0.00

£250,160.00

£8,150,000.00

£8,400,160.00

£250,160.00

Fabricate cellar deck

100%

£7,317,920.00

£7,317,920.00

£7,200,000.00

£0.00

£117,920.00

£7,200,000.00

£7,317,920.00

£117,920.00

Turbine generators

100%

£2,786,080.00

£2,786,080.00

£2,560,000.00

£0.00

£226,080.00

£2,560,000.00

£2,786,080.00

£226,080.00

Fuel gas systems

100%

£2,891,680.00

£2,891,680.00

£3,180,000.00

£0.00

-£288,320.00

£3,180,000.00

£2,891,680.00

-£288,320.00

Fabricate flare boom

100%

£4,159,840.00

£4,159,840.00

£4,430,000.00

£0.00

-£270,160.00

£4,430,000.00

£4,159,840.00

-£270,160.00

Cooling systems

75%

£3,823,788.00

£3,700,440.00

£3,217,500.00

-£123,348.00

£482,940.00

£4,290,007.37

£4,933,920.00

£643,912.63

Seawater pumping systems

35%

£1,645,810.67

£1,114,904.00

£584,500.00

-£530,906.67

£530,404.00

£1,670,005.18

£3,185,440.00

£1,515,434.82

Connect both decks

90%

£3,279,680.00

£2,951,712.00

£3,627,000.00

-£327,968.00

-£675,288.00

£4,030,003.16

£3,279,680.00

-£750,323.16

Install flare boom

20%

£1,830,976.00

£523,136.00

£156,000.00

-£1,307,840.00

£367,136.00

£780,001.10

£2,615,680.00

£1,835,678.90

Coalescer systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£0.00

£2,346,720.00

£2,346,720.00

Gas dehydration systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£2,823,680.00

£2,823,680.00

£0.00

Water injection systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£3,288,640.00

£3,288,640.00

£0.00

Gas compression systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£3,405,920.00

£3,405,920.00

£0.00

Onshore commissioning

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£1,603,040.00

£1,603,040.00

£0.00

MS project allows to calculate the earned value of the project considering project schedule as mentioned in the following table: the SPI value can be effective in determining whether the project is on schedule or late from the estimations. The activities with SPI value equals one is moving as per the project plan developed in planning phase (Eskerod and Jaspen 2016). The value less than 1 denotes the activity is lagging in schedule and hence, modifications are required to complete the project within estimated timeline.

Task Name

% Work Complete

Planned Value – PV (BCWS)

Earned Value – EV (BCWP)

SV

SV%

SPI

Fabricate upper deck

100%

£8,400,160.00

£8,400,160.00

£0.00

0%

1

Fabricate cellar deck

100%

£7,317,920.00

£7,317,920.00

£0.00

0%

1

Turbine generators

100%

£2,786,080.00

£2,786,080.00

£0.00

0%

1

Fuel gas systems

100%

£2,891,680.00

£2,891,680.00

£0.00

0%

1

Fabricate flare boom

100%

£4,159,840.00

£4,159,840.00

£0.00

0%

1

Cooling systems

75%

£3,823,788.00

£3,700,440.00

-£123,348.00

-3%

0.97

Seawater pumping systems

35%

£1,645,810.67

£1,114,904.00

-£530,906.67

-32%

0.68

Connect both decks

90%

£3,279,680.00

£2,951,712.00

-£327,968.00

-10%

0.9

Install flare boom

20%

£1,830,976.00

£523,136.00

-£1,307,840.00

-71%

0.29

Coalescer systems

0%

£0.00

£0.00

£0.00

0%

0

Gas dehydration systems

0%

£0.00

£0.00

£0.00

0%

0

Water injection systems

0%

£0.00

£0.00

£0.00

0%

0

Gas compression systems

0%

£0.00

£0.00

£0.00

0%

0

Onshore commissioning

0%

£0.00

£0.00

£0.00

0%

0

Risk Register

MS project allows to calculate the earned value of the project considering project budget as mentioned in the following table: the CPI value can be effective in determining whether the project is under budget or going over budget. The activities with SPI value equals one is moving as per the project plan developed in planning phase. The value less than 1 denotes the activity is lagging in schedule and hence, modifications are required to complete the project within estimated timeline. “For the result is more than 1, as in 1.25, then the project is under budget, which is the best result. A CPI of 1 means the project is on budget, which is also a good result. A CPI of less than 1 means the project is over budget (Hagney 2016).”

Task Name

Planned Value – PV (BCWS)

Earned Value – EV (BCWP)

CV

CV%

CPI

BAC

EAC

VAC

TCPI

Fabricate upper deck

£8,400,160.00

£8,400,160.00

£250,160.00

3%

1.03

£8,400,160.00

£8,150,000.00

£250,160.00

0

Fabricate cellar deck

£7,317,920.00

£7,317,920.00

£117,920.00

2%

1.02

£7,317,920.00

£7,200,000.00

£117,920.00

0

Turbine generators

£2,786,080.00

£2,786,080.00

£226,080.00

8%

1.09

£2,786,080.00

£2,560,000.00

£226,080.00

0

Fuel gas systems

£2,891,680.00

£2,891,680.00

-£288,320.00

-10%

0.91

£2,891,680.00

£3,180,000.00

-£288,320.00

-0

Fabricate flare boom

£4,159,840.00

£4,159,840.00

-£270,160.00

-6%

0.94

£4,159,840.00

£4,430,000.00

-£270,160.00

-0

Cooling systems

£3,823,788.00

£3,700,440.00

£482,940.00

13%

1.15

£4,933,920.00

£4,290,007.37

£643,912.63

0.72

Seawater pumping systems

£1,645,810.67

£1,114,904.00

£530,404.00

48%

1.91

£3,185,440.00

£1,670,005.18

£1,515,434.82

0.8

Connect both decks

£3,279,680.00

£2,951,712.00

-£675,288.00

-23%

0.81

£3,279,680.00

£4,030,003.16

-£750,323.16

-0.94

Install flare boom

£1,830,976.00

£523,136.00

£367,136.00

70%

3.35

£2,615,680.00

£780,001.10

£1,835,678.90

0.85

Coalescer systems

£0.00

£0.00

£0.00

0%

0

£2,346,720.00

£0.00

£2,346,720.00

1

Gas dehydration systems

£0.00

£0.00

£0.00

0%

0

£2,823,680.00

£2,823,680.00

£0.00

1

Water injection systems

£0.00

£0.00

£0.00

0%

0

£3,288,640.00

£3,288,640.00

£0.00

1

Gas compression systems

£0.00

£0.00

£0.00

0%

0

£3,405,920.00

£3,405,920.00

£0.00

1

Onshore commissioning

£0.00

£0.00

£0.00

0%

0

£1,603,040.00

£1,603,040.00

£0.00

1

Network Diagram using MS project

For the first table, the SPI value is one for all the completed task and is relatively same as compare to the percentage of work being done. It means that the work is being completed as it was planned and the project is on schedule (Heagney 2016). For the uncompleted tasks, the values are lower than 1 and hence, the project deliveries are not meeting the estimated amount of work being done.

Moving forward towards the earned value cost indicator, it is clear that the value of CPI for all the tasks are greater than 1 excluding three activities. It means that other than those three activities, the project progress is under budget (Lock 2017). For the three activities, the project is going over budget and hence, the project needs a monitoring and controlling plan that can assure that the future deliveries can fill this gap and result the project to be cost effective.

Task

Description

Duration (weeks)

Predecessor/s

Fixed costs

£M

New duration

New budget

£M

K

Gas dehydration systems

4

J

2.7

2

1.6

L

Water injection systems

6

G,H

3.1

2

3

M

Gas compression systems

6

I

3.2

3

1.1

N

Onshore commissioning

8

K,L,M

1.1

5

2.25

The above calculated data can be used for modifying the existing or planned information of the project and hence, new Gantt chart can be prepared that will alternatively result in the new critical path for the project:

Early Start

Early Finish

Late Start

Late Finish

Slack

Mon 01-01-18

Fri 26-01-18

Mon 01-01-18

Fri 26-01-18

0 wks

Mon 01-01-18

Fri 12-01-18

Mon 01-01-18

Fri 12-01-18

0 wks

Thu 08-02-18

Wed 21-03-18

Thu 08-02-18

Wed 21-03-18

0 wks

Fri 19-01-18

Thu 01-02-18

Fri 19-01-18

Thu 01-02-18

0 wks

Fri 19-01-18

Thu 15-02-18

Fri 19-01-18

Thu 15-02-18

0 wks

Mon 09-04-18

Fri 01-06-18

Mon 09-04-18

Fri 01-06-18

0 wks

Mon 09-04-18

Fri 29-06-18

Mon 09-04-18

Fri 29-06-18

0 wks

Mon 09-04-18

Fri 20-04-18

Mon 09-04-18

Fri 04-05-18

2 wks

Fri 27-04-18

Thu 07-06-18

Fri 27-04-18

Fri 22-06-18

2.2 wks

Mon 04-06-18

Fri 29-06-18

Mon 04-06-18

Fri 29-06-18

0 wks

Mon 02-07-18

Fri 13-07-18

Mon 02-07-18

Fri 13-07-18

0 wks

Mon 02-07-18

Fri 13-07-18

Mon 02-07-18

Fri 13-07-18

0 wks

Fri 08-06-18

Thu 28-06-18

Mon 25-06-18

Fri 13-07-18

2.2 wks

Mon 16-07-18

Fri 17-08-18

Mon 16-07-18

Fri 17-08-18

0 wks

There are two critical paths identified that can be considered for further project delivery for which we have options: FJKN and GLN that will alternatively take 19 weeks each to complete the project for rest of the activities after 30th April 2018. Since FJKN consist of four activities it can be considered as the critical path to be followed for further modifications in the project for delivering the project successfully. GLN path has not been recommended as it has less number of activities.

For the instance, if all the proposed recommendations are applied than the project delivery can be made earlier and could be delivered by 27th July 2018. Considering the cost and schedule all options can look better however, it will result timeloss and quality of the project as the resources are being much overloaded after that. And so, modifications on the existing critical path can be opted for further project modification (Fleming and Koppleman 2016). It will no doubt be helpful and effective in managing the timeline, cost and quality of the project.

The project will be completed in rest 19 days that will result in the following earned value analysis:

Earned Value analysis can be stated as:

Task Name

% Work Complete

Planned Value – PV (BCWS)

Earned Value – EV (BCWP)

AC (ACWP)

SV

CV

EAC

BAC

VAC

<New Summary Task>

50%

£0.00

£0.00

£33,105,000.00

£0.00

-£33,105,000.00

£48,146,880.00

£0.00

-£48,146,880.00

   Fabricate upper deck

100%

£8,400,160.00

£8,400,160.00

£8,150,000.00

£0.00

£250,160.00

£8,150,000.00

£8,400,160.00

£250,160.00

   Fabricate cellar deck

100%

£7,317,920.00

£7,317,920.00

£7,200,000.00

£0.00

£117,920.00

£7,200,000.00

£7,317,920.00

£117,920.00

   Turbine generators

100%

£2,786,080.00

£2,786,080.00

£2,560,000.00

£0.00

£226,080.00

£2,560,000.00

£2,786,080.00

£226,080.00

   Fuel gas systems

100%

£2,891,680.00

£2,891,680.00

£3,180,000.00

£0.00

-£288,320.00

£3,180,000.00

£2,891,680.00

-£288,320.00

   Fabricate flare boom

100%

£4,159,840.00

£4,159,840.00

£4,430,000.00

£0.00

-£270,160.00

£4,430,000.00

£4,159,840.00

-£270,160.00

   Cooling systems

75%

£3,823,788.00

£3,700,440.00

£3,217,500.00

-£123,348.00

£482,940.00

£4,290,007.37

£4,933,920.00

£643,912.63

   Seawater pumping systems

35%

£1,645,810.67

£1,114,904.00

£584,500.00

-£530,906.67

£530,404.00

£1,670,005.18

£3,185,440.00

£1,515,434.82

   Connect both decks

90%

£3,279,680.00

£2,951,712.00

£3,627,000.00

-£327,968.00

-£675,288.00

£4,030,003.16

£3,279,680.00

-£750,323.16

   Install flare boom

20%

£1,830,976.00

£523,136.00

£156,000.00

-£1,307,840.00

£367,136.00

£780,001.10

£2,615,680.00

£1,835,678.90

   Coalescer systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£0.00

£2,346,720.00

£2,346,720.00

   Gas dehydration systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£2,823,680.00

£2,823,680.00

£0.00

   Water injection systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£3,062,880.00

£3,288,640.00

£225,760.00

   Gas compression systems

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£3,405,920.00

£3,405,920.00

£0.00

   Onshore commissioning

0%

£0.00

£0.00

£0.00

£0.00

£0.00

£2,564,400.00

£1,603,040.00

-£961,360.00

Conclusion

It can be concluded that the iron triangle can be an effective strategy for assuring that the project managers deliver their section of work and manage the entire project thoroughly. Various project management approaches have been used in this project including the project progress monitoring and implementing the changes those are best suited for the successful delivery and management of the entire project. The MS project software has been used for predicting and demonstrating the project planning and its constraints. The proposed changes can bring positive outcomes for the DBLC Company and manage the budget and schedule of the entire project. The above report demonstrates how delay in a single activity could reflect alterations in the entire project and how complex and crucial conditions could born.

I get to know that schedule and budget of the projects are always interrelated to each other and manipulations or uncertainties in either of the parameter could bring a drastic change in the overall delivery of the project. I also identified that even in small projects, high calculations and better decision-making are very crucial considering the planned progress and actual progress of the project. The iron triangle can be an efficient strategic approach towards assuring the project constraints’ deliveries as it has been planned to.   Projects have always a tail of risks those are capable of impacting the entire project, the project managers’ primary role is to analyse detect, and propose counters measures to the risks those could possibly influence the project in negative manner.  I performed the risk analysis for this project after discussing about the iron triangle. The risk register can be very crucial to build however, it is very informative and efficient in developing the strategies those could allow the project manager to fight them. As mentioned above, the iron triangle includes time, scope, budget, and quality of the project. I understand that all these parameters have significantly impact on others. The project cannot have any one parameter very high and effective and other one very low and of no use.  I used MS project throughout the entire report preparation and thus, I learnt very new knowledge that can be used in the future professional and personal development.

I noticed that the project manager of the DBLC had developed a sophisticated projectplan that could be an efficient and successful planning if followed strictly.  I used the same data for the preparation of the Gantt chart and the budgeting of the entire project and its activities using the MS project.  Calculation is not my very string subject however, I know about the formulas those could be used for solving the requirement file. However, I decided to  use the MS project software as it could save a lot of time and with exceptional errors.  Thus, the above projected results on simulating the project activities n MS project could be used for the successful delivery of the project. I have not very strong command over the MS project as, I wasnot in regular practice for using the MS project. So, I went to for the inline video tutorials by reputed engineer, business man, and project manager to enhance and improve my knowledge extent. I used those data and information in an effective and efficient manner.  Planning and budgeting plane can be smoothly proceeded, through the application of the software. It was very efficient tool that allowed e to get the project details exactly and accurately as it was demanded.  I learn how to deliver the necessary changes through setting a baseline of the project during its initiation stage. The monitoring of the entire project can be an efficient and effective strategy focusing on the development and introduction of the new strategies those could finally meet the project needs and requirements.

I also performed the cost benefit analysis and noticed that the paper calculations cannot be easy and it can also impact on the reliability of the final results. However, MS project allows us to bring those data in the form of tables in the meantime.  I learnt various options and selection of the strategies in the MS project that can allow the users to instantly calculate the big calculations and make decisions accordingly. Earned Value analysis was the most difficulty section for throughout the entire project lifecycle.  And so, the calculation needs to be accurate in manner to make sure that the recommendations could be made that can bring project towards the success. I am not very smart in using the MS project and so, I took various helps from the YouTube that helped me in strengthening the knowledge related to the various applications of the MS project. I identified that I will need practice on using the MS project in much efficient manner. I will be continuously use the MS project for better understanding on the various applications those could be delivered in an efficient way and in no time through using this software.

References

Basu, R., 2017. Fundamentals of Project Management. In Managing Quality in Projects (pp. 27-46). Routledge.

Eskerod, P. and Jepsen, A.L., 2016. Project stakeholder management. Routledge.

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Heagney, J., 2016. Fundamentals of project management. Amacom.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Lock, D., 2017. The essentials of project management. Routledge.

Meredith, J.R., Mantel, S.J., Shafer, S.M. and Sutton, M.M., 2014. Project management in practice. Wiley.

Muller, R., 2017. Project governance. Routledge.

Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Routledge.

Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP