Development Of A New System For UNICEF Child Care

Current Issues and Impact on UNICEF Child Care

The purpose of the project is development of a new system in UNICEF child care. The child care facility has been facing issues in managing their donations and maintaining stock of their products. UNICEF child care takes care of children ageing between 6 weeks up to 13years of age and has grown popular due to their contribution to the society. The new system will help them manage their organizations in a better way.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The UNICEF child care takes care of children by providing them with babysitters, food, nannies and teachers. The organization has flourished over the time and they serve more than 2500 people on a daily basis. However, the payment and ordering processes are still manual which is problematic for the parents to pay and for the centre head to order required inventory. The parents have to go to the firm’s website to get the bank details and make a transfer of funds to the respective account. This process is time consuming and cumbersome for the parents. Moreover, the organization does not have automated system for ordering and inventory management which causes wastage of resources.

As opined by ul Hassan, Ahmad and Zuhaira, (2018), project statement is developed to outline the project deliverables, requirements, constraints and assumptions. The key success factors are also defined within the project so that it can be followed to attain the desired result. The current project will consist of developing a new information system which will facilitate in online transaction of funds and management of inventory in a better way so that resource wastage can be reduced.

As stated by Alias et al., (2014), project objectives are the direct and intended outcomes which are derived based on the scope statement. This will be developed according to the requirements of the stakeholders. In this current project, the objectives are as follows:

  • To investigate the current issues and identify the requirements of the new system
  • To communicate and discuss with the team members about the project objectives to distinguish between their job roles
  • To spot the hardware and software required for the new system
  • To develop the new system for facilitate the online transaction and inventory management
  • To incorporate the system within the organization model
  • Testing of the new developed system for required modifications
  • Reshaping and launching of the new system

Project requirements are tasks or conditions that will have to be fulfilled in order to complete the project.  The requirements in a project will provide a clear picture of the things that will have to be done (Haron et al., 2017). These will be used to align the resources along with the objectives of the project. There are major benefits in effectively defining the requirements of the project are cost reduction, effective change management, increase in success rate of the project and improvement in communication among the stakeholders. The requirements of the current project are as follows:

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
  • To identify the requirements for the change management initiative
  • Developing a system that can auto generate  response when payment has been made
  • To develop systems that keep records of all the clients
  • To develop inventory management system to avoid wastage of resources

Project Statement

The restrictions put on the action of the project team are known as project context. There are mainly six project constraints that they will have to deal with and they are quality, time, resources, risk, cost and scope (Shiohama et al., 2016). The constraint triangle shows that scope, time and cost are the three primary factors affecting the quality of the project. The project constraints are interrelated and impact of one factor will have a significant influence on the other factors in the project. The constraints in the project are time, resource and budget. The time span is fixed and cannot be changed so the project will have to manage risk factors and uncertainties in a better way. The resources are limited due to the budget constraints so over allocation of resources will have to be avoided. The project team will have to develop an effective communication plan so that role of every member is well defined. Therefore, the project manager will have to monitor and control each process on a regular process which will be essential for maintaining the integrity of the project.

In every project there are certain predefined assumptions which have to be taken into consideration before executing the project (Kerzner, 2017). The assumptions of the project are as follows:

  • The internal stakeholders, departments and sponsors of the project have fully supported the project that has been undertaken
  • The headquarters will fulfil the additional requirements for the successful execution of the project.
  • The project purpose and objective have been communicated to all the departments

As stated by Muriana and Vizzini (2017), risk management plays a vital role in success of the project and it consists of identification of risk factors, evaluation of the risk factors and mitigation of  the risk factors based on their priority. The risk factors can be categorized into three categories such as external risk, internal risk and technical risk. The risk factors are mitigated according to level of damage they can have on the project. The probability of occurrence of each of the risk factors is the measure of risk priority.

External risk

Risk Description

Delay in delivery of the hardware components

External issues that it unexpected

Priority

Low

Medium

Summary

New hardware components are required to effective develop the new automated system. The delay in delivery of the components is totally dependent on the vendor. This will have an impact on the overall project.

In a project scenario there are large numbers of uncertainties which may occur due to irregularities.

Affected Area

It will affect the implementation phase of the project.  This will increase the time frame for this phase.

As the risk is unexpected it may affect all the phases or any particular phase.

Mitigation Plan

This can be mitigated by developing components internally or by order the supply with a considerable buffer period.

Therefore, development of risk register effectively can be used to identify the unexpected risk factors.

Internal risk

Risk

Delay in approval of the design for the new system

Customization failure in the implementation phase

Sudden requirement changes

Priority

Medium

High

High

Summary

Approval of the new design system is crucial as it covers the first phase of the project so without the approval the project cannot proceed further.

 The new development system will have to suit the needs of the organization and if it is unable to do so then the overall project is a failure. Therefore, effective customization is essential for organizational success.

 Scope creep is a common phenomenon in the project. However, changes in requirement after a certain phase will increase the cost and time span of the project.

Affected Area

The time span of the project is affected.

 This will affect the implementation and closure phase and increase the time span in the later part of the project.

The scope creep affects the overall projects as it leads to the change in the project deliverables.

Mitigation Plan

Effective development of a communication plan will be able to mitigate this risk factor

 The initiation phase will have to be executed effectively to identify the customization requirements.

 It has to be clearly defined that all the changes within the project will be accepted within the first two phases otherwise the project cost and timeframe will be heavily affected.

Chow, Woodford and Lambe, (2014), states the input processes within the project required for achieving the desired goals of the stakeholders. The inputs in a project will depend on the project processes and they can be like documents, equipment, information, software, plan and money. However, the outputs in the projects are mainly recognized as deliverables in the project. This will consist of components like software, hardware, contracts, applications and assessment results.  In this present project, the deliverables of the projects are as follows:

Task Name

Duration

Start

Finish

Online ordering and deposit system

173 days

Fri 4/6/18

Tue 12/4/18

1.0 Initiation phase

40 days

Fri 4/6/18

Thu 5/31/18

2.0 Planning phase

25 days

Fri 6/1/18

Thu 7/5/18

3.0 Execution phase

105 days

Fri 7/6/18

Thu 11/29/18

4.0 Closure phase

3 days

Fri 11/30/18

Tue 12/4/18

As put forward by Montoya and Persson, (2017), the achievements in different phases of the task are known as the project milestone. These are tasks within the project schedule having duration of zero days and they do not have any influence on the overall timeframe of the project. However, these are important tasks as it signifies completion of important phases within a project. However, this will change depending upon the project approach taken by the organizations.

Task Name

Duration

Start

Finish

Online ordering and deposit system

173 days

Fri 4/6/18

Tue 12/4/18

Milestone 1: Project charter developed

0 days

Thu 5/31/18

Thu 5/31/18

Milestone 2: System and network requirements developed

0 days

Thu 7/5/18

Thu 7/5/18

Milestone 3: New system launched

0 days

Thu 11/29/18

Thu 11/29/18

Milestone 4: Project completed

0 days

Tue 12/4/18

Tue 12/4/18

Project Objectives

The summary schedule shows that different phases and tasks that have to be performed in each of the phases (Kerzner & Kerzner, 2017).  The project schedule shows that the overall estimated time for project is 173 days and the project will commence from 6th April, 2018 and the finish date of the project is 4th December, 2018.  However, there may be changes in the schedule depending upon the risk factors and changes in the deliverables of the project. Even though the buffer time has been allocated to each of the tasks there are certain uncertainties which can affect the project time span. The schedule shows the allotted time for each of the tasks and the schedule for the current project are as follows:

Task Name

Duration

Start

Finish

Online ordering and deposit system

173 days

Fri 4/6/18

Tue 12/4/18

1.0 Initiation phase

40 days

Fri 4/6/18

Thu 5/31/18

1.1 New system requirement identification

10 days

Fri 4/6/18

Thu 4/19/18

1.2 functional requirement mapping

15 days

Fri 4/20/18

Thu 5/10/18

1.3 user requirement mapping

8 days

Fri 4/20/18

Tue 5/1/18

1.4 Develop initial project charter draft

7 days

Fri 5/11/18

Mon 5/21/18

1.5 Conduct meetings with authorities and team members

3 days

Tue 5/22/18

Thu 5/24/18

1.6 Final project charter development

4 days

Fri 5/25/18

Wed 5/30/18

1.7 Deploy project charter

1 day

Thu 5/31/18

Thu 5/31/18

Milestone 1: Project charter developed

0 days

Thu 5/31/18

Thu 5/31/18

2.0 Planning phase

25 days

Fri 6/1/18

Thu 7/5/18

2.1 Identification of the hardware requirements

10 days

Fri 6/1/18

Thu 6/14/18

2.2 Identification of the software requirements

6 days

Fri 6/1/18

Fri 6/8/18

2.3 Identification of the network development requirements

10 days

Fri 6/1/18

Thu 6/14/18

2.4 Regulate the Database management requirements

15 days

Fri 6/15/18

Thu 7/5/18

Milestone 2: System and network requirements developed

0 days

Thu 7/5/18

Thu 7/5/18

3.0 Execution phase

105 days

Fri 7/6/18

Thu 11/29/18

3.1 Existing hardware and software Upgradation

35 days

Fri 7/6/18

Thu 8/23/18

3.2 Appropriate Database developed

25 days

Fri 7/6/18

Thu 8/9/18

3.3 New system incorporation

20 days

Fri 8/24/18

Thu 9/20/18

3.4 Testing the new system

30 days

Fri 9/21/18

Thu 11/1/18

3.5 Identification of the required modification

5 days

Fri 11/2/18

Thu 11/8/18

3.6 Incorporating the changes

10 days

Fri 11/9/18

Thu 11/22/18

3.7 New system launch

5 days

Fri 11/23/18

Thu 11/29/18

Milestone 3: New system launched

0 days

Thu 11/29/18

Thu 11/29/18

4.0 Closure phase

3 days

Fri 11/30/18

Tue 12/4/18

4.1 Reviewing the overall project and processes

1 day

Fri 11/30/18

Fri 11/30/18

4.2 Project Document

2 days

Mon 12/3/18

Tue 12/4/18

4.3 Signing off of the project members

1 day

Mon 12/3/18

Mon 12/3/18

Milestone 4: Project completed

0 days

Tue 12/4/18

Tue 12/4/18

The summary budget shows the estimated budget of the overall project along with the budget for each of the tasks (Abran, 2015). However, the budget will change if there is change in resource allocation and deliverables. Moreover, the risk factors may affect the time span of the project which in turn will have an impact on the budget. The budget of the current project has been described in detail in the table below:

Task Name

Resource Names

Cost

Online ordering and deposit system

$42,784.00

1.0 Initiation phase

$12,488.00

1.1 New system requirement identification

Project Manager, Public officer, Software Developer, System Engineer

$4,080.00

1.2 functional requirement mapping

Software Developer, System Engineer

$2,280.00

1.3 user requirement mapping

Project Manager

$1,280.00

1.4 Develop initial project charter draft

Project Manager

$1,120.00

1.5 Conduct meetings with authorities and team members

Chairman, Project Manager, Public officer, Software Developer, System Engineer, Treasurer, Vice Chairman

$2,928.00

1.6 Final project charter development

Project Manager

$640.00

1.7 Deploy project charter

Project Manager

$160.00

Milestone 1: Project charter developed

$0.00

2.0 Planning phase

$5,032.00

2.1 Identification of the hardware requirements

System Engineer

$800.00

2.2 Identification of the software requirements

Software Developer

$432.00

2.3 Identification of the network development requirements

Software Developer, System Engineer

$1,520.00

2.4 Regulate the Database management requirements

Software Developer, System Engineer

$2,280.00

Milestone 2: System and network requirements developed

$0.00

3.0 Execution phase

$21,360.00

3.1 Existing hardware and software Upgradation

Software Developer, System Engineer

$5,320.00

3.2 Appropriate Database developed

Software Developer, System Engineer

$3,800.00

3.3 New system incorporation

Software Developer, System Engineer

$3,040.00

3.4 Testing the new system

Software Developer, System Engineer

$4,560.00

3.5 Identification of the required modification

Project Manager, Software Developer, System Engineer

$1,560.00

3.6 Incorporating the changes

Software Developer, System Engineer

$1,520.00

3.7 New system launch

Project Manager, Software Developer, System Engineer

$1,560.00

Milestone 3: New system launched

$0.00

4.0 Closure phase

$3,904.00

4.1 Reviewing the overall project and processes

Chairman, Project Manager, Public officer, Software Developer, System Engineer, Treasurer, Vice Chairman

$976.00

4.2 Project Document

Project Manager, Public officer, Software Developer, System Engineer, Chairman, Treasurer, Vice Chairman

$1,952.00

4.3 Signing off of the project members

Chairman, Project Manager, Public officer, Software Developer, System Engineer, Treasurer, Vice Chairman

$976.00

Milestone 4: Project completed

$0.00

Name

Start

Finish

Remaining Work

Cost

Project Manager

Fri 4/6/18

Tue 12/4/18

376 hrs

$7,520.00

System Engineer

Fri 4/6/18

Tue 12/4/18

1,576 hrs

$15,760.00

Software Developer

Fri 4/6/18

Tue 12/4/18

1,544 hrs

$13,896.00

Public officer

Fri 4/6/18

Tue 12/4/18

136 hrs

$1,632.00

Chairman

Tue 5/22/18

Tue 12/4/18

56 hrs

$1,680.00

Vice Chairman

Tue 5/22/18

Tue 12/4/18

56 hrs

$1,400.00

Treasurer

Tue 5/22/18

Tue 12/4/18

56 hrs

$896.00

Conclusion

Thus, it can be concluded from the project charter that an effective plan has been developed for developing a new system for the UNICEF child care service. However, the implementation and the success of the project will depend on the mitigation of the risk factor, development of an effective communication plan and identifying the project requirements in a correct way. 

References

Abran, A. (2015). Software project estimation: the fundamentals for providing high quality information to decision makers. John Wiley & Sons.

Alias, Z., Zawawi, E. M. A., Yusof, K., & Aris, N. M. (2014). Determining critical success factors of project management practice: A conceptual framework. Procedia-Social and Behavioral Sciences, 153, 61-69.

Chow, A. F., Woodford, K. C., & Lambe, N. (2014). Using project deliverables and project management for timely completion of student projects. Journal of Emerging Trends in Economics and Management Sciences, 5(3), 323.

Haron, A., Sahibuddin, S., Yusoff, H., & Osman, M. H. (2017, May). Systematic Approach Based on Best Practices to Develop Requirements Engineering (RE) Guideline in an Organization. In Information and Communication Technology (PICICT), 2017 Palestinian International Conference on (pp. 126-131). IEEE.

Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Montoya, J. H., & Persson, K. A. (2017, April). The Materials Project: Milestones, Challenges, and Opportunities in High-Throughput Computational Materials Science. In Meeting Abstracts (No. 35, pp. 1666-1666). The Electrochemical Society.

Muriana, C., & Vizzini, G. (2017). Project risk management: A deterministic quantitative technique for assessment and mitigation. International Journal of Project Management, 35(3), 320-340.

Shiohama, R., Washizaki, H., Kuboaki, S., Sakamoto, K., & Fukazawa, Y. (2016). Investigating the relationship between project constraints and appropriate iteration length in agile development through simulations. International Journal of Computer Applications in Technology, 54(4), 311-322.

ul Hassan, I., Ahmad, N., & Zuhaira, B. (2018). Calculating completeness of software project scope definition. Information and Software Technology, 94, 208-233.

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP