The WBS of the “Work Breakdown Structure” would consist of each and every task that would be accomplished accordingly. The “Work Breakdown Structure” would be developed in a 3-4 level WBS format and would be developed in “Indented format” as well (Budczies et.al, 2012). The WBS that has been developed below is a clear projection of the array of tasks that would be essential for accomplishing the entire task in an effective manner.
This would be a typical Gantt chart consisting of activity estimation, activity duration, dependencies among each activity (Osentoski et.al, 2011, May). This particular step consists of developing the Gantt chart including the tasks and activities undertaken for accomplishing each of the project deliverables in consideration to the time schedule along with the amount of money allotted for each of the task. However in order for developing the Gantt chart, it is necessary to develop the project schedule and include crucial information describing the individual task along with the time frame they are to be achieved within.
Task Name |
Duration |
Start Date |
Finish Date |
Percentage Completed |
Precedes |
Resource Name |
Application Development Timetable |
125 Days |
10-5-17 |
10-9-17 |
0% |
||
Scope |
3-5 Days |
10-5-17 |
13-5-17 |
0% |
||
Ascertaining Project Scope |
4 Hrs |
13-5-17 |
13-5-17 |
0% |
Management |
|
Securing Sponsorship |
1 Day |
13-5-17 |
14-5-17 |
0% |
2 |
Management |
Defining Primary Resources |
1 Day |
14-5-17 |
15-5-17 |
0% |
3 |
Project Manager |
Securing Fundamental Resources |
1 Day |
15-5-17 |
16-5-17 |
0% |
4 |
Project Manager |
Scope Complete |
0 Day |
16-5-17 |
16-5-17 |
0% |
5 |
|
Analyzing Software Obligations |
28 Days |
16-5-17 |
13-6-17 |
0% |
||
Carrying Out Need Analysis |
10 Days |
13-6-17 |
23-6-17 |
0% |
6 |
Analyst |
Sketching Primary Software Application |
3 Days |
23-6-17 |
26-5-17 |
0% |
8 |
Analyst |
Arranging Primary Budget |
2 Days |
26-5-17 |
28-5-17 |
0% |
9 |
Project Manager |
Assessing Software Specification Budget |
4 Hrs |
28-5-17 |
28-5-17 |
0% |
10 |
Project Analyst And Manager |
Incorporating Feedback On Software Specification |
1 Day |
28-5-17 |
29-5-17 |
0% |
11 |
Analyst |
Developing Delivery Timeline |
1 Day |
29-5-17 |
30-5-17 |
0% |
12 |
Project Manager |
Gathering Approval For Advancing |
4 Hrs |
30-5-17 |
30-5-17 |
0% |
13 |
Management And Project Manager |
Securing Required Resources |
10 Days |
30-5-17 |
9-6-17 |
0% |
14 |
Project Manager |
Analysis Complete |
0 Days |
9-6-17 |
9-6-17 |
0% |
15 |
|
Design |
23 Days |
9-6-17 |
2-7-17 |
0% |
||
Assessing Principal Software Specification |
2 Days |
2-7-17 |
4-7-17 |
0% |
16 |
Analyst |
Mounting Functional Specification |
21 Days |
4-7-17 |
25-7-17 |
0% |
Analyst |
|
Use Case 1 |
2 Days |
25-7-17 |
27-7-17 |
0% |
18 |
Analyst |
Use Case 2 |
3 Days |
27-7-17 |
30-7-17 |
0% |
20 |
Analyst |
Use Case 3 |
1 Day |
30-7-17 |
31-7-17 |
0% |
21 |
Analyst |
Use Case 4 |
1 Day |
31-7-17 |
1-8-17 |
0% |
22 |
Analyst |
Use Case 5 |
1 Day |
1-8-17 |
2-8-17 |
0% |
23 |
Analyst |
Interface Space |
8 Days |
2-8-17 |
10-8-17 |
0% |
||
Interface 1 |
1 Day |
10-8-17 |
11-8-17 |
0% |
24 |
Analyst |
Interface 2 |
1 Day |
11-8-17 |
12-8-17 |
0% |
26 |
Analyst |
The time-phased budget would be developed in consideration to the “bottom-up estimating” (Singhal & Shukla, 2012). The budget would typically be based over the resource allocation to each one of the activities. The budget would involve various activities in consideration to the project and activities. This can be described as the calculation of the amount of money that has been distributed among various tasks mentioned in the WBS and the Gantt chart displayed above. The budget for this project would reflect a typical budget that usually is used while developing any project (Subashini & Kavitha, 2011). The fundamental aspects of this particular time phased budget would include the below mentioned aspects:
The amount that has been allotted for carrying out this entire project was approximately 50,000 AUD (Australian Dollar) that is accountable for carrying out each and every task that has been planned under this project.
Training cost of employees 5000 AUD
Training the administrative workers 1000 AUD
Sum of training cost 6000 AUD
Equipment along with material costs including servers and the backup severs did cost around 6000, 5000 and 7000
Labor costs
Average salary 100 AUD
Programmer 5000 AUD
Database manager 3000 AUD
Project analyst 5000 AUD
Operation analyst 5000 AUD
Interface manager 2900 AUD
Network analyst 5000 AUD
Total amount 50,000 AUD
The risk register would entirely be based over the typical and probable risk that might hamper the proceedings of any project (Tipton & Nozaki, 2012).
Risk name |
Description |
Probability |
Schedule risk |
Schedule risk refers to the idea of not achieving tasks at the prescribed time schedule, which eventually can hamper the entire pace of the project and might even hamper the final outcome. |
Although, project managers are there to monitor the time period factor along with various other aspects as well, ignoring this particular factor would draw major lag in the process. The probability of this particular risk is “Moderate”. |
Operational risk |
As the name suggests, this particular pattern of risk is associated with operations of the project, which means this type of risk would hamper the entire operation ability of the team. For example: failed systems or threats from external events |
High; despite of the fact that the project manager would always be there to ensure the flawlessness of the entire operation, such risks are beyond one’s capability |
Technical risks |
Technical faults often hamper the entire process causing severe consequences |
High |
Budget risks |
As the schedule increases, it affects the budget as well, some factors are beyond organizational control, which can affect the proceedings |
High |
The quality management plan would be based over how important it is to maintain the quality of the any project that is being undertaken. Software development procedure without the management plan for maintaining quality is not possible (Weinberger et.al, 2011, September). The sole purpose of this particular agenda is to define the quality standard along with the pathway for maintaining the quality. The team members including administrative to developers, each one of the workers are bound to comply with the rules, regulations and the standards of this particular plan. The fundamental of this plan revolves around certain perspectives and purposes, including:
This particular document would consist of a checklist regarding if every task and activity has been accomplished or not. This is a document that every software development project manager has to present upon completion of the entire project. It is one of the most important and obvious roles of the project manager to ensure that each and every task that has been included in the WBS (Work Breakdown Structure) and following documents have been achieved and fulfilled successfully (Winesett, 2012). This particular document can also be referred as the evidence showcasing a successful achievement of the complete project. The closure checklist for this project would certainly follow the fundamental or conventional template and would include the following aspects:
References:
Budczies, J., Klauschen, F., Sinn, B. V., Gy?rffy, B., Schmitt, W. D., Darb-Esfahani, S., & Denkert, C. (2012). Cutoff Finder: a comprehensive and straightforward Web application enabling rapid biomarker cutoff optimization. PloS one, 7(12), e51862.
Charland, A., & Leroux, B. (2011). Mobile application development: web vs. native. Communications of the ACM, 54(5), 49-53.
Corral, L., Sillitti, A., & Succi, G. (2012). Mobile multiplatform development: An experiment for performance analysis. Procedia Computer Science, 10, 736-743.
Espie, C. A., Kyle, S. D., Williams, C., Ong, J. C., Douglas, N. J., Hames, P., & Brown, J. S. (2012). A randomized, placebo-controlled trial of online cognitive behavioral therapy for chronic insomnia disorder delivered via an automated media-rich web application. Sleep, 35(6), 769-781.
Felt, A. P., Greenwood, K., & Wagner, D. (2011, June). The effectiveness of application permissions. In Proceedings of the 2nd USENIX conference on Web application development (pp. 7-7).
Finifter, M., & Wagner, D. (2011, June). Exploring the relationship between Web application development tools and security. In USENIX conference on Web application development.
Han, W., Yang, Z., Di, L., & Mueller, R. (2012). CropScape: A Web service based application for exploring and disseminating US conterminous geospatial cropland data products for decision support. Computers and Electronics in Agriculture, 84, 111-123.
Heitkötter, H., Hanschke, S., & Majchrzak, T. A. (2012, April). Evaluating cross-platform development approaches for mobile applications. In International Conference on Web Information Systems and Technologies (pp. 120-138). Springer Berlin Heidelberg.
Horner, J. (2011). RApache: Web application development with R and Apache.
Osentoski, S., Jay, G., Crick, C., Pitzer, B., DuHadway, C., & Jenkins, O. C. (2011, May). Robots as web services: Reproducible experimentation and application development using rosjs. In Robotics and Automation (ICRA), 2011 IEEE International Conference on (pp. 6078-6083). IEEE.
Singhal, M., & Shukla, A. (2012). Implementation of location based services in Android using GPS and Web services. IJCSI International Journal of Computer Science Issues, 9(1), 237-242.
Subashini, S., & Kavitha, V. (2011). A survey on security issues in service delivery models of cloud computing. Journal of network and computer applications, 34(1), 1-11.
Tipton, H. F., & Nozaki, M. K. (2012). Information Security Management Handbook, Volume 6. Auerbach Publications.
Weinberger, J., Saxena, P., Akhawe, D., Finifter, M., Shin, R., & Song, D. (2011, September). A systematic analysis of XSS sanitization in web application frameworks. In European Symposium on Research in Computer Security (pp. 150-171). Springer Berlin Heidelberg.
Winesett, J. (2012). Web Application development with Yii and PHP. Packt Publishing Ltd.
We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.
Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.
Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.
Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.
Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.
Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.
We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.
Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.
You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.
Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.
Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.
You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.
You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.
Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.
We create perfect papers according to the guidelines.
We seamlessly edit out errors from your papers.
We thoroughly read your final draft to identify errors.
Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!
Dedication. Quality. Commitment. Punctuality
Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.
We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.
We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.
We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.
We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.