Calculation Of Quantities Of Materials For Building Project

Bore excavation for 300mm diameter piers

This assessment involves calculation of quantities of materials of different elements of the building in project 1. There are nine tasks to be solved.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The summary of take-off quantities of materials s provided in Table 1

Diameter of piers = 300 mm

Depth of piers = 2.5 m

The piers are located at every corner/beam intersection and spaced at a maximum of 1800mm.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

From the structural detail of the ground floor, the number of piers is 53.

The volume of one pier is calculated as follows: πr2h (where r = radius of the pier and h = depth of the pier).

Volume = π x (0.15m)2 x 2.5m = 0.1767 m3

Total volume of bored excavation for 53 piers = 0.1767 m3 x 53 = 9.366 m3

This is done by removing vegetation and top soil not exceeding 300mm deep starting from the existing ground level so as to prepare the site generally for laying the foundation and ground floor slab. However, it does not include detailed excavation of the slab and beams. The bulk excavation is done 1m beyond the house walls to create adequate working space. It is assumed that the depth of bulk excavation is 300mm. The bulk excavation is measured from the structural details.

The bulk excavation volume is determined by multiplying the length, width and depth of the ground area to be excavated.

Some excavated material will be needed to be used as fill because of the ground is uneven as shown by the contours in the building site plan. About half of the excavated material will be used as fill to level the ground for the slab construction. Therefore the amount of fill material needed is about 37m3

The concrete for each of the elements on the ground is determined by multiplying the length with the width and depth of that particular element as follows

Ground floor slab

6.3m x 5.17m x 0.1m = 3.26m3

5.18m x 5.17m x 0.1m = 2.68m3

6.3m x 5.16m x 0.1m = 3.25m3

5.18m x 5.16m x 0.1m = 2.67m3

3.63m x 4.61m x 0.1m = 1.67m3

Beams

Edge beams (EB):

2 x 12.83m x 0.45m x 0.42m = 4.85m3

1 x 10.97m x 0.45m x 0.42m = 2.07m3 

1 x 10.82m x 0.45m x 0.42m = 2.04m3

2 x 3.63m x 0.45m x 0.42m = 1.37m3

Internal beams (IB):

1 x 11.48m x 0.35m x 0.35m = 1.41m3

1 x 10.97m x 0.45m x 0.35m = 1.73m3

1 x 4.61m x 0.45m x 0.35m = 0.73m3

Patio slab

5.17m x 0.35m x 0.1m = 0.18095m3

[(1.32m x 6.35m) – (0.35m x 0.24m)] x 0.1m = 0.8298m3 

Pad footings

2 x 0.9m x 1.2m 0.45m = 0.972m3 

The net measure of SL72 reinforcing mesh is determined by calculating the net area of ground floor slab and patio slab as follows

Ground slab:

11.93m x 10.97m = 130.87m2

3.63m x 4.61m = 16.73m2

Patio slab:

5.17m x 0.35m = 1.81m2

[(1.32m x 6.35m) – (0.35m x 0.24m)] = 8.3m2 

Bulk excavation

Net ground area = 130.87m2 + 16.73m2 + 1.81m2 + 8.3m2 = 157.71m2

The number of sheets needed to complete the ground slabs is determined by dividing the net ground area by the effective cover of one sheet. The effective cover of reinforcing mesh sheet is 5.8m x 2.2m with 400mm lap. Thus the number of sheets is calculated as follows

The length of trench mesh needed is determined by calculating the total length of trenches needed for the ground slab. The trench lengths are determined as follows:

3 x 12.83m = 38.49m

3 x 10.97m = 32.91m

2 x 4.08m = 8.16m

1 x 4.61m = 4.16m

Total = 38.49m + 32.91m + 8.16m + 4.16m = 83.72m

The structural steel bars used are of diameter 12 mm and spaced at 200mm apart. The weight of this bars is 0.89kg or 0.00089 tonnes per meter.

 (Civilology, 2019)

Length of main bars = no. of main bars x length of one main bar (Hamakareen, 2018); (Krishna, 2019).

Length of main bars = (32 x 5.11m) + (32 x 4.97m) = 163.52m + 159.04m = 322.56m

Length of main bars = (27 x 5.11m) + (27 x 4.97m) = 137.97m + 134.19m = 272.16m

Length of main bars = (19 x 4.51m) = 85.69m

Length of main bars = (8 x 5.45m) = 43.6m

Total length of main bars = 322.56m + 272.16m + 85.69m + 43.6 = 724.01m

Length of distribution bars = no. of distribution bars x length of one distribution bar

Length of distribution bars = (29 x 6.2m) + (29 x 5.08m) = 179.8m + 147.32m = 327.12m

Length of distribution bars = (26 x 6.2m) + (26 x 5.08m) = 161.2m + 132.08m = 293.28m

Length of distribution bars = (24 x 3.63m) = 87.12m

Length of distribution bars = (29 x 1.32m) = 38.28m

Total length of distribution bars = 327.12m + 293.28m + 87.12m + 38.28m= 745.8m 

Net measure

The net measure includes the area of walls of the first floor rooms excluding wet areas. The height of the first floor rooms is 2450mm.

Rumpus: 4.5m + 5.52m + 1.99m + 3.36m + 1.71m = 17.07m x 2.45m = 41.82m2

Gallery: 6.06m + 4.16m = 10.22m x 2.45m = 25.04m2 

Bed 1: 10.54m + 8.12m = 18.66m x 2.45m = 45.72m2

Bed 2: 7.08m + 6.98m = 14.06m x 2.45m = 34.45m2

Bed 3: 3.54m + 3.23m + 2.14m + 2.22m + 2.15m = 13.28m x 2.45m = 32.54m2 

Bed 4: 2.66m + 3.34m + 3.03m + 3.34m = 12.37m x 2.45m = 30.31m2

Net area of walls = 41.82m2 + 25.04m2 + 45.72m2 + 34.45m2 + 32.54m2 + 30.31m2 = 209.88m2

Number of plasterboard sheets

Standard size of plasterboards is 2400mm long and 1200mm wide. Area of one sheet is:

2.4m x 1.2m = 2.88m2

The length of skirting needed for the first floor rooms is as follows:

Rumpus: 4.5m + 5.52m + 1.99m + 3.36m + 1.71m = 17.07m

Gallery: 6.06m + 4.16m = 10.22m

Bed 1: 10.54m + 8.12m = 18.66m

Bed 2: 7.08m + 6.98m = 14.06m

Bed 3: 3.54m + 3.23m + 2.14m + 2.22m + 2.15m = 13.28m

Bed 4: 2.66m + 3.34m + 3.03m + 3.34m = 12.37m

Ensuite: 6.8m + 8.12m + 3.62m + 4.98m = 23.52m

Bath: 6.06m + 6.52m = 12.58m

Hall: 4.16m + 2.22m + 4.3m + 3.04m + 1.59m = 15.31m

Balcony: 11.04m + 3.04m = 14.08m

Total = 17.07+10.22+18.66+14.06+13.28+12.37+23.52+12.58+15.31+14.08 = 151.15m   

The length of one skirting is 2.7m 

First is to calculate the floor area of the individual gro9und floor rooms

Family room: 4.08m x 5.03m = 20.52m2 

Meals room: 2.17m x 4.589m = 9.96m2

Kitchen: 4.589m x 5.87m = 26.94m2

Foyer/stairs: 5.5m x 1.71m = 9.41m2

Net floor area = 20.52+9.96+26.94+9.41 = 66.83m2

Allow 10% wastage =

Size of tiles used is 20cm by 20cm

Area of one tile = 0.2m x 0.2m = 0.04m2

No of tiles =

Table 1: Material quantities take-off

Item

Particulars

Unit

Qnty

Rate

Cost

1

Bored excavation for 300mm diameter piers

m3

10

53/π/0.15/0.15/2.5                    9.37

2

Bulk excavation (excluding detailed excavation for slab and beams)

m3

74

14.83/13.87/0.3           61.71

5.08/7.51/0.3               11.45

                                    73.16

3

N25 concrete to the ground slab, beams, patio slab and pad footing

m3

30

3.1

Ground floor slab

6.3/5.17/0.1                  3.26

5.18/5.17/0.1                2.68

6.3/5.16/0.1                  3.25

5.18/5.16/0.1                2.67

3.63/4.61/0.1                1.67       13.53

3.2

Edge beams

2/12.83/0.45/0.42          4.85

1/10.97/0.45/0.42          2.07

1/10.82/0.45/0.42           2.04

2/3.63/0.45/0.42             1.37     10.33

3.3

Internal beams

1/11.48/0.35/0.35           1.41

1/10.97/0.45/0.35           1.73

1/4.61/0.45/0.35             0.73      3.87

3.4

Patio slab

5.17/0.35/0.1                  0.18

1.32/6.35/0.1                  0.84

0.35/0.24/0.1            (0.0084)   1.01

3.5

Pad footings

2/0.9/1.2/0.45                 0.97     0.97

                                                   29.71

4

SL72 reinforcing mesh to ground slabs

 

4.1

Net measure of ground slabs

m2

158

11.93/10.97        130.87

3.63/4.61            16.73

5.17/0.35            1.81

1.32/6.35            8.38

0.35/0.24            (0.084)

                           157.71

4.2

Number of reinforcement sheets

No

13

157.71/(5.8/2.2)-1 12.36

5

SL12TM

m

84

3/12.83             38.49

3/10.97             32.91

2/4.08               8.16

1/4.61               4.16

                          83.72

6

Structural steel of ground floor

t

1.31

6.1

Main bars

t

0.65

32/10.08/0.00089         0.29

27/10.08/0.00089         0.24

19/4.51/0.00089           0.08

8/5.45/0.00089             0.04

                                     0.65

6.2

Distribution bars

29/11.28/0.00089          0.29

t

0.66

26/11.28/0.00089          0.26

24/3.63/0.00089            0.08

29/1.32/0.00089            0.03

                                      0.66

                                      1.31

7

Plasterboard

7.1

Net measure

m2

210

17.07/2.45                41.82

10.22/2.45                25.04

18.66/2.45                45.72

14.06/2.45                34.45

12.28/2.45                32.54

12.37/2.45                30.31

                                 209.88

7.2

Number of plasterboard sheets

no

73

209.88/(2.88)-1      72.88

8

66x18mm finished DAR primed pine skirting

8.1

Net measure

m

152

Bed 1        18.66

Bed 2        14.06

Bed 3        13.28

Bed 4        12.37

Ensuite      23.52

Bath          12.58

Rumpus    17.07

Gallery     10.22

Hall          15.31

Balcony   14.08

               151.15

Number of skirting pieces

no

56

151.15/(2.7)-1      55.98

9

Ceramic floor tiles

9.1

Net floor area

m2

74

Family room

4.08/5.03       20.52

Meals room

2.17/4.589      9.96

Kitchen

4.589/5.87      26.94

Foyer/stair

5.5/1.71          9.41

                      66.83/1.1    73.51

9.2

Number of tiles

no

1838

73.51/(0.04)-1      1837.75

Civilology. (2019). How to Calculate Steel Quantity for Slab? – Reinforcement Calculation . Retrieved from Civilology: https://www.civilology.com/bar-bending-schedule-for-slab/

Hamakareen, M. (2018). How to calculate steel quantity for slab, footing and column? Retrieved from The Constructor: https://theconstructor.org/practical-guide/calculate-steel-quantity-slab-footing-column/25533/

Krishna. (2019, January 12). Bar Bending Schedule [BBS] Estimate of Steel in Building Construction. Retrieved from Civil Read: https://civilread.com/bar-bending-schedule-bbs/

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Services offered

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code ESSAYHELP